Ill. Admin. Code tit. 41, § 175.320 - Scheduling of UST Activity
a) All
permitted activity shall be scheduled with OSFM. There are 2 sets of procedures
for scheduling permitted activity, Operational Safety Inspection (OSI) or
Performance Assurance Inspection (PAI). The procedures for scheduling OSI
Activity (Date Certain) are set forth in subsection (c) and for PAI Activity
(Date and Time Certain) are set forth in subsection (d). A licensed contractor
shall have at least one employee certified for the UST activity for which the
permit was issued actively supervising in person the UST activity being
performed on the site. At all times during permitted activity, including at all
STSS inspections, including any final inspection, there shall be an employee or
individual contractor certified in the work to be done on the job site.
Subcontractors are not "employees" for this purpose.
b) No permitted and scheduled OSI or PAI
activity can be performed outside the schedule unless changes have been
approved in advance by OSFM. Notice of cancellation must be received by OSFM no
later than 6:00 a.m. of the scheduled date and the revised date of the work
must be at least one complete working day after OSFM receipt of the revised job
schedule request. The day of receipt is not included in the advance
notice/receipt calculation. A new permit and fee will be required when there is
a failure to meet any of the schedules. This includes not being present for
inspection, not being completely ready for inspection, violation of any
technical requirements for the permitted work, allowing permit to expire before
completing the final inspection, or not canceling the job within the allowed
time frame. Failure to meet the schedules also includes a failure to complete
all UST work and site preparation necessary for the STSS inspection, including
any necessary testing and related corrections, prior to the time the STSS is
scheduled to first arrive. Upon these events, the permit is considered void and
no work may commence until a new permit is issued and the work scheduled
pursuant to this Section.
c) OSI
(Date Certain) Activity. OSI activity includes UST installations, installation
or removal of over 20 feet or 50% of the total piping run or an entire pipe
run, tank removal, abandonment-in-place, lining and lining inspection, tank
entry and any hot work. Regarding UST installation, scheduled OSFM inspections
are required for an air test on the tank prior to installation, tank
installation, air test on primary lines, air test on secondary containment,
hydrostatic test on containments prior to backfill, and final inspection.
Regarding installation of an entire pipe run, OSFM inspections are required for
both the primary and secondary air test on the piping and a hydrostatic test on
containments prior to backfill, and final inspection. Any additional inspection
in follow-up to tank penetration via hot work, including a final lining
inspection and tank precision testing, shall be scheduled as a PAI inspection.
For a listing of OSI activities, see Appendix A to this Part.
1) For OSI activity, the licensed contractor
shall have a granted permit before scheduling with OSFM to establish a specific
date and time that is not less than one complete working day before the
anticipated date of the permitted activity. A UST contractor portal for the
on-line submission of permit applications and the scheduling of permitted work
can be found at the UST Applications and Forms page for the DPCS at
https://webapps.sfm.illinois.gov/USTPortal/Home/Login?ReturnUrl=%2fUSTPorta.
2) Only the licensed contractor or an
employee of the contractor (this does not include subcontractors) may schedule
the work with OSFM.
3) For OSI
activity, the work will not be allowed to be done unless an STSS is on
site.
4) At the final OSI (Date
Certain) inspection on a lining, a licensed contractor representative is not
required to be on site but scheduling of the final inspection is
required.
d) PAI (Time
and Date Certain) Activity. PAI permitted activity includes upgrades not
involving piping installation, repairs not involving hot work, or cathodic
protection activity. PAI activities will be scheduled for a period of at least
2 working hours (between 8:30 a.m. and 3:30 p.m. on State business days) and
subsequent activities that interfere with the ability to inspect will not
proceed until the time period is over. Tank and line precision testing and
cathodic protection testing following permitted activity must be scheduled with
OSFM pursuant to subsection (d)(2). For a listing of OSI activities, see
Appendix A.
1) Permitted PAI Activity. The
licensed contractor shall have a granted permit before scheduling the permitted
activity with OSFM not less than one complete working day before the
anticipated date of work. A UST contractor portal for the on-line submission of
permit applications and the scheduling of permitted work can be found at the
website cited in subsection (c)(1). The Division of Petroleum and Chemical
Safety (DPCS) will transmit an e-mail confirmation of scheduling approval back
to the contractor within one working day. Work shall not commence until the
contractor receives this confirmation. Only the licensed contractor or an
employee of the contractor (this does not include subcontractors) may schedule
the work with OSFM.
2)
Non-permitted PAI Activity. Non-permitted PAI activity includes tank and line
precision testing and cathodic protection testing following permitted activity.
The licensed contactor or contractor's employee shall schedule the activity
with OSFM in advance of the anticipated work. Only the contractor or an
employee of the contractor (this does not include subcontractors) may schedule
the work with OSFM. A UST contractor portal for the on-line scheduling of
non-permitted work can be found at the website cited in subsection
(c)(1).
3) When only installing a
bag, wristband or spike anode for cathodic protection in a containment sump, or
a spill containment device with or without a riser replacement, or an overfill
prevention device, or when an interstitial sensor is being reclassified from
regulated to non-regulated, at the final PAI (Time and Date Certain)
inspection, a licensed contractor representative is not required to be on site,
but scheduling of the final inspection is required.
4) Any time an emergency repair permit is
issued, the licensed contractor shall electronically schedule and complete the
final inspection within 10 days after issuance of the permit.
e) UST Installation.
1) For all UST installations, the final
inspection shall not be scheduled without prior submission of:
A) the completed electronic Notification for
Underground Storage Tanks form and its accompanying Authorization to Submit
(available at
https://sfm.illinois.gov/about/divisions/petroleum-chemical-safety/applications-and-forms.html);
B) the completed OSFM on-line forms for all
required testing; and
C) if
applicable, the completed motor fuel dispensing permit application.
2) Other kinds of permitted work
do not require submission of this Notification form.
f) There shall be no transfer or sale of
product from a UST until the UST is in compliance with OSFM rules and any
required final inspection has been completed. Any request to fill a required
minimal amount of fuel necessary to perform compliance testing must be
submitted electronically by an OSFM-licensed contractor and approved by OSFM in
advance. A Drop Fuel Request form is available at the UST contractor portal at
the website cited in subsection (c)(1). A depositor may make one deposit of a
regulated substance to a newly installed or newly lined tank to provide
ballast; that fuel shall not be sold or dispensed until the required decal is
obtained.