Ill. Admin. Code tit. 44, § 8.8092 - Effect on Current Contracts
Current CDB contracts may be terminated when a contractor is determined to be non-responsible and it is in the public interest to do so, whether or not the non-responsibility has a direct connection with the current contract. Contracts may be terminated with or without further action on the vendor's prequalification.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.