Ill. Admin. Code tit. 77, § 210.1500 - Notice of Violation and Plan of Correction
a) Upon determination that the licensee or
applicant is in violation of the Act or this Part, the Department shall issue a
written Notice of Violation and request a plan of correction. The notice shall
specify the violation(s), and shall instruct the licensee or applicant to
submit a plan of correction to the Department within 10 days after receipt of
the Notice.
b) Within the ten-day
period, a licensee or applicant may request additional time for submission of
the plan of correction. The Department may extend the period for submission of
the plan of correction for an additional 30 days, when the Department finds
that corrective action by the Model to abate or eliminate the violation(s) will
require substantial capital improvement. The Department will consider the
extent and complexity of necessary physical plant repairs and improvements and
any impact on the health, safety, or welfare of the patients of the Model in
determining whether to grant a requested extension.
c) Each plan of correction shall be based on
an assessment by the Model of the conditions or occurrences that are the basis
of the violation(s) and an evaluation of the practices, policies, and
procedures that have caused or contributed to the conditions or occurrences.
Evidence of such assessment and evaluation shall be maintained by the Model.
Each plan of correction shall include:
1) A
description of the specific corrective action the Model is taking, or plans to
take, to abate, eliminate, or correct the violation(s) cited in the
Notice;
2) A description of the
steps that will be taken to avoid future occurrences of the same and similar
violation(s); and
3) A specific
date by which the corrective action will be completed.
d) Submission of a plan of correction shall
not be considered an admission by the Model that the violation(s) has
occurred.
e) The applicant or
licensee may submit additional information in response to the Notice of
Violation that it believes will clarify the condition or alleged violation(s).
The Department will consider the information in reviewing the applicant's or
licensee's response and the plan of correction.
f) The Department shall review each plan of
correction to ensure that it provides for the abatement, elimination, or
correction of the violation. The Department shall reject a submitted plan only
if it finds any of the following deficiencies:
1) The plan does not address the conditions
or occurrences that are the basis of the violation and an evaluation of the
practices, policies, and procedures that have caused or contributed to the
conditions or occurrences.
2) The
plan is not specific enough to indicate the actual actions the Model will be
taking to abate, eliminate, or correct the violation.
3) The plan does not provide for measures
that will abate, eliminate, or correct the violation.
4) The plan does not provide steps that will
avoid future occurrences of the same and similar violations.
5) The plan does not provide for timely
completion of the corrective action, considering the seriousness of the
violation, any possible harm to the patients, and the extent and complexity of
the correction action.
g) The Department shall notify the licensee
or applicant if the plan of correction is rejected, including specific reasons
for the rejection of the plan. The Model shall submit a modified plan that
addresses the requirements of subsection (c) of this Section within five days
after receipt of notice of rejection.
h) If a licensee or applicant fails to make a
timely submission of a modified plan of correction, or such modified plan is
not acceptable to the Department, a plan of correction shall be specified and
imposed by the Department.
i) The
Department shall verify the completion of the corrective action required by the
plan of correction within the specified time period during subsequent
investigations, surveys, and evaluations of the Model.