Ill. Admin. Code tit. 77, § 518.2160 - Submission of Architectural Plans
a) New Construction, Addition, or Major
Alteration
1) When construction is
contemplated, either for new buildings or additions or alterations to existing
buildings coming within the scope of this Part, design development drawings and
outline specifications shall be submitted to the Department for review.
Approval of design development drawings and specifications shall be obtained
from the Department prior to starting final working drawings and
specifications. The Department will provide comments or approval within 30
working days after receipt of the drawings and specifications and the
submission being deemed complete.
2) Final Drawings
A) The final working drawings and
specifications shall be submitted to the Department for review and approval
prior to beginning of construction. For final approval to remain valid,
contracts shall be signed within one year after the approval date. Alternate
methods of design development and construction may be acceptable subject to the
approval of the Department. The Department will provide comments or approval
within 30 working days after receipt of the final drawings and the submission
being deemed complete.
B) The
Department shall be notified upon the award of construction
contracts.
3) Any
contract modifications that affect or change the function, design, or purpose
of a facility shall be submitted to the Department for approval prior to
authorizing the modifications. The Department will provide comments or approval
within 60 working days after receipt of the drawings and
specifications.
4) Upon 90% of
completion, the pre-occupancy certification package shall be submitted to the
Department.
5) As-built drawings
shall be maintained by the freestanding emergency center.
b) Minor Alterations and Remodeling. Minor
alterations or remodeling changes that do not affect the structural integrity
of the building, that do not change functional operation, that do not affect
fire safety, and that do not increase capacity over that for which the FEC is
licensed need not be submitted for approval.
c) Alterations of Water Supply, Plumbing and
Drainage. No system of water supply, plumbing, sewage, garbage or refuse
disposal shall be installed, nor any such existing system materially altered or
extended, until complete plans and specifications for the installation,
alteration or extension have been submitted to the Department and have been
reviewed and approved.
d) Codes and
Standards
1) Nothing stated in this Part
shall relieve the licensee from compliance with building codes, ordinances and
regulations that are enforced by city, county or local jurisdictions.
2) The recommendations of the International
Building Code shall apply insofar as those recommendations are not in conflict
with the standards set forth in this Part or with NFPA 101.
A) The portions of the International Building
Code requiring smoke detectors in all patient rooms and automatic door closers
on all patient room doors are hereby specifically excluded from these
requirements.
B) The International
Building Code is intended as a model code for municipalities with no building
code of their own.
C) NFPA 101-A
shall apply only if the Department determines that the proposed equivalent
system is safe and does not constitute a hazard to the life and safety of the
staff and patients.