Ill. Admin. Code tit. 77, § 600.200 - Provisional Certification
a) A
local health department that serves one or more counties and that is not a
certified local health department may make application for provisional
certification. The application shall be submitted to the Department by letter,
memorandum or similar document signed by an authorized representative and shall
include a written commitment to the Department to complete IPLAN or an
equivalent to IPLAN within two years after provisional certification is
granted.
b) Upon submission of a
complete application, the Department shall have 60 days to review the
application. Provisional certification shall be granted by the Department to
any local health department that meets the requirements of subsection (a).
Provisional certification shall expire upon certification of the local health
department or two years after the date provisional certification was granted,
whichever is shorter. Provisional certification may be renewed as provided in
subsection (c).
c) A local health
department that has been granted provisional certification may apply for
renewal of provisional certification. The application shall be made at least 30
days prior to expiration of the provisional certification by submitting to the
Department a letter, memorandum or similar document signed by an authorized
representative. The application shall describe activities that the local health
department performed during the current term of provisional certification and
future activities that will be undertaken during the renewal term that would be
expected to result in the completion of IPLAN or an equivalent to IPLAN.
1) Renewal applications that are complete and
received by the Department no later than 30 days prior to the expiration of
provisional certification shall be considered by the Department.
2) The first renewal of provisional
certification shall be made if the Department determines, on the basis of the
application, that the applicant can be expected to complete IPLAN or an
equivalent to IPLAN by conclusion of the renewal term.
3) The second renewal of provisional
certification shall be made if the Department determines, on the basis of a
written explanation submitted by the local health department, in addition to
the application for renewal specified in this subsection (c), that the
applicant can be expected to complete IPLAN or an equivalent to IPLAN by
conclusion of the second renewal term. The explanation shall include
documentation of the incomplete elements of IPLAN or an equivalent to IPLAN
with their expected completion dates and the reasons why the local health
department did not complete IPLAN or an equivalent to IPLAN within the first
renewal term.
4) A renewal of
provisional certification granted by the Department shall not exceed 12
months.
5) No more than two
renewals of provisional certification shall be granted to a local health
department.
d) A
provisionally certified local health department is eligible to apply for a
Local Health Department Development Grant, pursuant to 77 Ill. Adm. Code
610.
e) The Department may conduct
an on-site review of the local health department and those documents necessary
to determine substantial compliance with this Section.
Notes
Amended at 22 Ill. Reg. 14474, effective July 24, 1998
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.