Ill. Admin. Code tit. 77, § 855.450 - Commencement of Work
The contractor shall not begin abatement work until the following requirements have been met:
a) Enclosure systems shall be constructed and
tested.
b) All pre-abatement
submissions, notifications, postings and permits shall be provided and are
satisfactory to the project manager.
c) All equipment for abatement, cleanup and
disposal shall be on hand.
d) All
worker training and licensing shall be completed.
e) Arrangements shall be made for building
security.
f) The number of
clearance air samples and the specific sample locations shall be established in
conjunction with the air sampling professional before abatement activity begins
(see Section 855.470).
g) The contractor shall receive written
permission from the building owner to commence abatement. Such written
permission shall be submitted to the Department attached with the Notice of
Asbestos Abatement Form provided by the Department.
h) The building owner shall notify all
parents, faculty and staff of the pending abatement project and notify the
contractor with written verification of such notification. Such written
verification shall be submitted to the Department by the contractor attached to
the Notice of Asbestos Abatement Form provided by the Department.
i) The contractor shall be responsible for
providing personal protection for its employees according to the OSHA
Construction Standard
29 CFR
1926.1101 (effective October 11,
1994).