Ill. Admin. Code tit. 77, § 905.95 - Illinois Raised Filter Beds
a)
Illinois raised filter bed disposal systems shall have a filter loading rate of
4 gallons per square foot per day for residential systems of up to 1,500 GPD
flows. Non-residential systems of any size or residential systems in excess of
1,500 GPD shall use a filter loading rate of 2.5 gallons per square foot per
day. The system shall be designed in accordance with Appendix A, Illustration
X, Exhibits A through E.
b) An
aeration batch treatment system that has been approved by NSF in accordance
with NSF Standard 40 shall be used. The aeration tank volume shall hold at
least 2 times the average daily wastewater flow for residential use (including
the use of a garbage disposal). Non-residential systems shall have a tank
volume size of 3 times the daily wastewater flow. Multiple tanks shall be used
to achieve the volume required. Multiple tanks require connection at the bottom
of each tank for flow equalization.
c) Filter beds shall not exceed 600 square
feet. If a larger area is needed, multiple beds shall be used, separated by a
minimum distance of 15 feet, using a common mantle. The filter beds can be
placed at any point on the mantle to accommodate existing ground
contours.
d) The filter length
shall not exceed 3 times the width.
e) The sand filter media shall have an
effective size of 0.5 to 2.0 millimeters, a uniformity coefficient of less than
3.5, and a 30-inch depth.
f) The
mantle shall be sized in accordance with the formula A = QT/25, where A =
Mantle Area, Q = Quantity of wastewater per day, and T = Percolation time of
the original soil in minutes per inch. (See Appendix A, Illustration X, Exhibit
E to convert soil investigation information to T (percolation time).)
g) The mantle shall be at least equal to the
area of the filter bed. The mantle shall not be designed for percolation rates
that exceed 120 minutes per inch.
h) The mantle area is to be cut into original
soil to a depth of 6 inches and back-filled with 12 inches of torpedo sand that
is graded as FA1-FA8 in accordance with Standard Specifications for Road and
Bridge Construction (Illinois Department of Transportation).
i) The slope of the bottom of the mantle
shall be level, plus or minus one inch. The slope of the earth sidewalls of the
filter shall be a maximum of 3 feet horizontal to one foot vertical.
j) The mantle area shall be at least 12
inches deep. If the maximum high groundwater table is less than 6 inches from
the bottom of the filter bed, additional torpedo sand shall be used to increase
the isolation distance between the bottom of the filter bed and the high
groundwater table to at least 6 inches. Other separation distances (e.g., well,
property line) shall be measured from the toe of the filter bed.
k) The distribution piping (4-inch perforated
pipe) shall be placed level to 15-inch centers in 12 inches of 3/4-inch
stone.
l) Sod shall be placed over
the filter beds and mantle.
Notes
Amended at 37 Ill. Reg. 14994, effective August 28, 2013