Ill. Admin. Code tit. 77, § 976.190 - Project Completion
Each grantee shall notify the Department within 30 calendar days following the project's completion.
a) The completion notice will provide a
notarized statement that certifies the following:
1) All project costs and sources of
funds;
2) That all funds attributed
to the grant award have been expended;
3) That the costs reported are the final
costs required to complete the project and there are no additional or
associated costs; and,
4) That no
portion of the grant was used to pay forany on-going operational costs,
outstanding debt or an endowment or other invested fund. (Section 2310-640(a)
of the Act)
b) The
notarized statement shall be signed by the grantee's Chief Executive
Officer.
c) Grantees whose projects
are subject to CON requirements shall also document that the Health Facilities
and Services Review Board has deemed the project complete (see 77 Ill. Adm.
Code 1130.770). Documentation shall
consist of a letter from the Health Facilities and Services Review Board
attesting that the project is complete.
d) Grantees whose projects are pending
approval in accordance with the requirements of the Hospital Licensing Act
shall also provide a copy of the Permanent Occupancy or Notice of System
Acceptance letter (whichever is applicable) issued by the Department.
e) Failure to provide the completion notice
within the prescribed time frame will result in the Department pursuing the
recovery of grant funds (see Section
976.140).