Ill. Admin. Code tit. 77, § 990.50 - Application Review Criteria
Applications shall be subject to a non-technical and technical review as follows:
a) Criteria for the
non-technical review shall include:
1)
adherence to the format specified in Section
990.40;
2) inclusion of all required forms as
specified in Section 990.40; and
3) the inclusion of a response to each
required item as specified in Section
990.40.
b) The technical review shall be based on the
following criteria:
1) the activities
identified by the applicant will lead to achievement of the
objectives;
2) the project
objectives are achievable in the stated time frame;
3) the evaluation methods measure progress
toward the identified objectives;
4) the budget required in Section
990.40(a)(6)
provides sufficient resources and justifies the need for funds to carry out the
project; and
5) continuation
applicants have documented the status of each activity in support of the
current year objectives and have provided an estimate of the extent to which
each current year objective will be met.