Ill. Admin. Code tit. 92, § 800.440 - Force Majeure
In the event that the recipient or a contractor is delayed, hindered in, or prevented from the performance of any act required by the contract by reason of any of the following:
a) strikes, lockouts, labor
troubles;
b) unduly harsh weather
conditions, not including foreseeable and ordinary adverse weather conditions
such as rain and snow, which prevent the normal performance of the
rehabilitation project;
c)
inability to procure materials;
d)
failure of power;
e) riots,
insurrection, or war; or,
f) any
Act of God;
the time of performance of such delayed party may be extended for a time period equal to such delay.