Iowa Admin. Code r. 199-45.2 - [Effective 7/16/2025] Scope

(1) This chapter applies to utilities, and distributed generation facilities seeking to operate in parallel with utilities, provided the facilities are not subject to the interconnection requirements of an affected system, the Federal Energy Regulatory Commission (FERC), the Midcontinent Independent System Operator Inc. (MI SO), the Southwest Power Pool (SPP), the Midwest Reliability Organization (MRO), or the SERC Reliability Corporation (SERC).
(2) If the nameplate capacity of the facility is greater than 10 megavolt amps (MVA), the interconnection customer and the utility shall start with the Level 4 review process and agreements under rule 199-45.11 (476) and modify the process and agreements as needed by mutual agreement. In addition, the interconnection customer and the utility shall start with the technical standards under rule 199-45.3 (476) and modify the standards as needed by mutual agreement. If the interconnection customer and the utility cannot reach mutual agreement, the interconnection customer may seek resolution through the dispute process in rule 199-45.12 (476).

Notes

Iowa Admin. Code r. 199-45.2
ARC 8859B, lAB 6/16/10, effective 7/21/10 Amended by IAB January 18, 2017/Volume XXXIX, Number 15, effective 2/22/2017 Adopted by IAB June 11, 2025/Volume XLVII, Number 25, effective 7/16/2025

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.