Iowa Admin. Code r. 199-9.5 - Restoration of agricultural lands
(1)
Topsoil survey.
a. Prior to the removal of any topsoil, the
pipeline company shall direct that a topsoil survey be performed under the
supervision of a certified professional soil scientist across the full extent
of the easement for any pipeline that requires a commission permit. A minimum
of three soil depths shall be physically measured in the field at each cross
section as follows:
(1) one on the left edge
of the easement;
(2) one at 15 feet
of the centerline of the pipeline on the working side of the right-of-way; and
(3) one on the right edge of the
working easement. Cross sections shall be taken a minimum of every 500 linear
feet for the full extent of the easement. Each parcel of land shall have a
minimum of two cross sections.
b. The pipeline company shall provide the
results of the topsoil survey to the county board of supervisors, county
inspector, county engineer, and affected persons at least six weeks prior to
commencing construction.
(2)
Topsoil separation and
replacement.
a.
Removal. Topsoil removal and replacement in accordance with
this rule is required for any open excavation associated with pipeline
construction unless otherwise provided in these rules. The actual depth of the
topsoil, as determined by a topsoil survey, shall be stripped from the full
extent of the easement. Topsoil shall also be removed and replaced in
accordance with these rules at any location where land slope or contour is
significantly altered to facilitate construction. Topsoil removal shall not
occur during wet conditions.
b.
Soil storage. The topsoil and subsoil shall be segregated,
stockpiled, and preserved separately during subsequent construction operations.
The stored topsoil and subsoil shall have sufficient separation to prevent
mixing during the storage period. Topsoil shall not be used to construct field
entrances or drives, or be otherwise removed from the property, without the
written consent of the landowner. Topsoil shall not be stored or stockpiled at
locations that will be used as a traveled way by construction equipment without
the written consent of the landowner.
c.
Stockpile stabilization.
Topsoil stockpiles shall be stabilized with seeding and mulch within 14
calendar days of stockpiling. Between October 15 and March 15, soil tackifier
shall be used in place of seeding and mulch.
d.
Topsoil removal not
required. Topsoil removal is not required where the pipeline is
installed by plowing, jacking, boring, or other methods that do not require the
opening of a trench. If provided for in a written agreement between the
pipeline company and the landowner, topsoil removal is not required if the
pipeline can be installed in a trench with a top width of 18 inches or
less.
e.
Backfill.
The topsoil and subsoil shall be replaced in the reverse order in which they
were excavated from the trench. The depth of the replaced topsoil shall conform
as near as possible to the depth of topsoil that was removed. Where excavations
are made for road, stream, drainage ditch, or other crossings, the original
depth of topsoil shall be replaced as near as possible.
(3)
Pumping of water from open
trenches.
a. In the event it becomes
necessary to pump water from open trenches, the pipeline company shall pump the
water in a manner that avoids damaging adjacent agricultural land. Damages from
pumping water from trenches include, but are not limited to, inundation of
crops and depositing of sediment in fields, pastures, and surface
drains.
b. If water-related damages
result from pumping water from trenches, the pipeline company shall either
compensate the landowner for the damages or restore the land, pasture, surface
drains, or similar land, to their preconstruction condition, at the landowner's
discretion.
c. Written permission
from the landowner is required before the pipeline company can pump water from
trenches onto land outside of the pipeline company's easement.
d. All pumping of water shall comply with
existing state drainage laws, local ordinances, and federal statutes.
(4)
Temporary and
permanent repair of drain tile.
a.
Pipeline clearance from drain tile. Where underground drain
tile is encountered, the pipeline shall be installed in such a manner that the
permanent tile repair can be installed with at least 12 inches of clearance
from the pipeline.
b.
Temporary repair. The following standards shall be used to
determine if temporary repair of agricultural drainage tile lines encountered
during pipeline construction is required.
(1)
Any underground drain tile damaged, cut, or removed and found to be flowing or
which subsequently begins to flow shall be temporarily repaired as soon as
practicable, and the repair shall be maintained as necessary to allow for its
proper function during construction of the pipeline. The temporary repairs
shall be maintained in good condition until permanent repairs are
made.
(2) Any underground drain
tile damaged, cut, or removed and found to not be flowing shall have the
upstream exposed tile line screened or otherwise protected to prevent the entry
of foreign material and small animals into the tile system. The downstream tile
line entrance shall be capped or filtered to prevent entry of mud or foreign
material into the line if water level rises in the trench.
c.
Marking. Any underground
drain tile damaged, cut, or removed shall be marked by placing a highly visible
flag in the trench spoil bank directly over or opposite such tile. This marker
shall not be removed until the tile has been permanently repaired and the
repairs have been approved and accepted by the county inspector. If proper
notice is given, construction shall not be delayed due to an inspector's
failure to be present on the site.
d.
Permanent repairs. Tile
disturbed or damaged by pipeline construction shall be repaired to its original
or better condition. Permanent repairs shall be completed within 14 days after
the pipeline is installed in the trench and prior to backfilling of the trench
over the tile line. The county inspector shall inspect each permanent repair
for compliance with this chapter. If proper notice is given, construction shall
not be delayed due to a county inspector's failure to be present on site.
Permanent repair and replacement of damaged drain tile shall be performed in
accordance with the following requirements:
(1) All damaged, broken, or cracked tile
shall be removed.
(2) Only
unobstructed tile shall be used for replacement.
(3) The tile furnished for replacement
purposes shall be of a quality, size, and flow capacity at least equal to that
of the tile being replaced.
(4)
Tile shall be replaced using a laser transit, or similar instrument or method,
to ensure that the tile's proper gradient and alignment are restored, except
where relocation or rerouting is required for angled crossings. Tile lines at a
sharp angle to the trench shall be repaired in the manner shown on Drawing No.
IUC PL-1 at the end of this chapter.
(5) The replaced tile shall be firmly
supported to prevent loss of gradient or alignment due to soil settlement. The
method used shall be comparable to that shown on Drawing No. IU C PL-1 at the
end of this chapter.
(6) Before
completing permanent tile repairs, all tile lines shall be examined visually by
televising on both sides of the trench over the full extent of the working
easement to check for tile that might have been damaged or misaligned by
construction equipment. If tile lines are found to be damaged, they must be
repaired to operate as well after construction as before
construction.
e.
Inspection. Prior to backfilling of the applicable trench
area, each permanent tile repair shall be inspected for compliance by the
county inspector. If proper notice is given, construction shall not be delayed
due to an inspector's failure to be present on site prior to
backfilling.
f.
Backfilling. The backfill surrounding the permanently repaired
drain tile shall be completed at the time of the repair and in a manner that
ensures that any further backfilling will not damage or misalign the repaired
section of the tile line. The county inspector shall inspect that backfill for
compliance with this chapter. If proper notice is given, construction shall not
be delayed due to an inspector's failure to be present on the site.
g.
Subsurface drainage.
Subsequent to pipeline construction and permanent repair, if it becomes
apparent the tile line in the area disturbed by construction is not functioning
correctly or that the land adjacent to the pipeline is not draining properly,
which can reasonably be attributed to the pipeline construction, the pipeline
company shall make further repairs or install additional tile as necessary to
restore subsurface drainage.
(5)
Removal of rocks and debris from
the easement.
a.
Removal. The topsoil, when backfilled, and the easement area
shall be free of all rock larger than three inches in average diameter not
native to the topsoil prior to excavation. Where rocks over three inches in
size are present, their size and frequency shall be similar to adjacent soil
not disturbed by construction. The top 24 inches of the trench backfill shall
not contain rocks in any greater concentration or size than exist in the
adjacent natural soils. Consolidated rock removed by blasting or mechanical
means shall not be placed in the backfill above the natural bedrock profile or
above the frost line. In addition, the pipeline company shall examine areas
adjacent to the easement and along access roads and shall remove any large
rocks or debris that may have rolled or blown from the right-of-way or fallen
from vehicles.
b.
Disposal. Rock that cannot remain in or be used as backfill
shall be disposed of at locations and in a manner mutually satisfactory to the
company and the landowner. Soil from which excess rock has been removed may be
used for backfill. All debris attributable to the pipeline construction and
related activities shall be removed and disposed of properly. For the purposes
of this rule, debris shall include spilled oil, grease, fuel, or other
petroleum or chemical products. Such products and any contaminated soil shall
be removed for proper disposal or treated by appropriate in situ
remediation.
(6)
Restoration after soil compaction and rutting.
a.
Agricultural restoration.
Agricultural land, including off right-of-way access roads traversed by heavy
construction equipment that will be removed, shall be deep tilled to alleviate
soil compaction upon completion of construction on the property. If the topsoil
was removed from the area to be tilled, the tillage shall precede replacement
of the topsoil. At least three passes with the deep tillage equipment shall be
made. Tillage shall be at least 18 inches deep in land used for crop production
and 12 inches deep on other lands and shall be performed under soil moisture
conditions that result in a maximum standard penetration test (SPT) reading of
300 psi pursuant to ASTM D1586-11 performed by a qualified person. Decompaction
shall not occur in wet conditions. Upon agreement, this tillage may be
performed by the landowners or tenants using their own equipment.
b.
Rutted land restoration.
Rutted land shall be graded and tilled until restored as near as practical to
its preconstruction condition. Rutting shall be remedied before any topsoil
that was removed is replaced.
(7)
Restoration of terraces,
waterways, and other erosion control structures. Existing soil
conservation practices and structures damaged by the construction of a pipeline
shall be restored to the elevation and grade existing prior to the time of
pipeline construction. Any drain tiles or flow diversion devices impacted by
pipeline construction shall be repaired or modified as needed. Soil used to
repair embankments intended to retain water shall be well compacted. Disturbed
vegetation shall be reestablished, including a cover crop when appropriate.
Restoration of terraces shall be in accordance with Drawing No. IUC PL-2 at the
end of this chapter. The county inspector shall inspect restoration of
terraces, waterways, and other erosion control structures for compliance with
this chapter. If proper notice is given, construction shall not be delayed due
to an inspector's failure to be present on the site.
(8)
Revegetation of untilled
land.
a.
Crop
production. Agricultural land not in row crop or small grain
production at the time of construction, including hay ground and land in
conservation or set-aside programs, shall be reseeded, including use of a cover
crop when appropriate, following completion of deep tillage and replacement of
the topsoil. The seed mix used shall restore the original or a comparable
ground cover unless otherwise requested by the landowner. If the land is to be
placed in crop production the following year, paragraph
9.5(9)"b" shall apply.
b.
Delayed crop production.
Agricultural land used for row crop or small grain production which will not be
planted in that calendar year due to the pipeline construction shall be seeded
with an appropriate cover crop following replacement of the topsoil and
completion of deep tillage. However, cover crop seeding may be delayed if
construction is completed too late in the year for a cover crop to become
established and in such instances is not required if the landowner or tenant
proposes to till the land the following year. The landowner may request ground
cover where the construction is completed too late in the year for a cover crop
to become established to prevent soil erosion.
c.
Weed control. On any
easement, including, but not limited to, construction easements and easements
relating to valve sites, metering stations, and compression stations, the
pipeline company shall provide for weed control in a manner that prevents the
spread of weeds onto adjacent lands used for agricultural purposes. Spraying
shall be done by a pesticide applicator that is appropriately licensed for
spraying of pesticide in Iowa. If the pipeline company fails to control weeds
within 45 days after receiving written notice from the landowner, the pipeline
company shall be responsible for reimbursing all reasonable costs of weed
control incurred by owners of adjacent land.
(9)
Future installation of drain tile
or soil conservation practices and structures.
a.
Future drain tile. The
pipeline company shall consult with affected persons regarding plans for future
drain tile installation. Where an affected person provides the pipeline company
with written plans prepared by a qualified tile technician for future drain
tile improvements before an easement is secured, the pipeline shall be
installed at a depth which will allow proper clearance between the pipeline and
the proposed future tile installation.
b.
Future practices and
structures. The pipeline company shall consult with any affected
person's plans for future use or installation of soil conservation practices or
structures. Where an affected person provides the pipeline company with a
design for such practice or structure prepared by a qualified technician before
an easement is secured, the pipeline shall be installed at a depth that will
allow for future installation of the planned soil conservation practice or
structure and that will retain the integrity of the pipeline.
(10)
Restoration of land
slope and contour. Upon completion of construction, the slope,
contour, grade, and drainage pattern of the disturbed area shall be restored as
near as possible to its preconstruction condition. However, the trench may be
crowned to allow for anticipated settlement of the backfill. Excessive or
insufficient settlement of the trench area, which visibly affects land contour
or undesirably alters surface drainage, shall be remediated by the pipeline
company by means such as regrading and, if necessary, import of appropriate
fill material. Disturbed areas in which erosion causes formation of rills or
channels, or areas of heavy sediment deposition, shall be regraded as needed.
On steep slopes, methods such as sediment barriers, slope breakers, or mulching
shall be used as necessary to control erosion until vegetation can be
reestablished. The county inspector shall inspect restoration of land slope and
contour for compliance with this chapter.
(11)
Restoration of areas used for
field entrances or temporary roads. Upon completion of construction
and land restoration, field entrances or temporary roads built as part of the
construction project shall be removed and the land made suitable for return to
its previous use. Areas affected shall be regraded as required by subrule
9.5(10) and deep tilled as required by subrule 9.5(6). If by agreement, or at
landowner request, and subject to any necessary approval by local public road
authorities, a field entrance or road is to be left in place, it shall be left
in a graded and serviceable condition. The county inspector shall inspect
restoration of areas used for field entrances or temporary roads for compliance
with this chapter.
(12)
Construction in wet conditions. The county inspector, in
consultation with the pipeline company and the landowner or person in
possession of the land pursuant to a lease, if present, shall determine when
construction should not proceed in a given area due to wet conditions. The
county inspector shall have the sole authority to determine whether
construction should be halted due to wet conditions. Construction in wet soil
conditions shall not commence or continue at times when or locations where the
passage of heavy construction equipment may cause rutting to the extent that
the topsoil and subsoil are mixed or underground drainage structures may be
damaged. To facilitate construction in wet soils, the pipeline company may
elect to remove and stockpile the topsoil from the traveled way, install mats
or padding, or use other methods acceptable to the county inspector. Topsoil
removal, storage, and replacement shall comply with subrule 9.5(2).
(13)
Access to land. Nothing
in this rule shall prohibit a landowner or person in possession of the land
pursuant to a lease from having access to the property. A landowner or person
in possession of the land pursuant to a lease shall not disrupt ongoing
construction and shall not compromise the safety considerations of the
construction. A landowner or person in possession of the land pursuant to a
lease shall abide by any and all safety instructions established by the
pipeline company during construction.