Iowa Code r. 199-45.4 - [Effective until 7/16/2025] Interconnection requests
(1)
Applicants seeking to interconnect a distributed generation facility shall
submit an interconnection request to the utility that owns the electric
distribution system to which interconnection is sought. Applicants shall
identify in the application if they are representing a group of customers that
are located in the same vicinity and whether the application requires a group
interconnection study. Applicants shall use the commission-approved
interconnection request forms and agreements that are provided on the
commission's website, iuc.iowa.gov.
(2) Preapplication request. Applicants may
request a preapplication report from the utility using the following process:
a. The utility shall designate an employee or
office from which information on the application process and on the affected
system can be obtained through an informal request from the applicant
presenting a proposed project for a specific site, which may include multiple
proposed individual interconnections in close proximity and related to one
project, such as a residential or commercial development proposing rooftop
solar on each premises or a multiturbine wind project. The name, telephone
number, and email address of such contact employee or office shall be made
available on the utility's website. Electric system information provided to the
applicant should include, to the extent such provision does not violate
confidentiality provisions of prior agreements or critical infrastructure
requirements, relevant, available system studies, interconnection studies, and
other materials useful for gaining an understanding of an interconnection at a
particular point on the utility's electric distribution system. The utility
shall comply with reasonable requests for such information.
b. In addition to the information described
in paragraph 45.4(2)"a," which may be provided in response to
an informal request, an applicant may submit a formal written request form
along with a nonrefundable fee of $300 for a preapplication report on a
proposed project at a specific site. The utility shall provide the
preapplication data described in paragraph 45.4(2)"a" to the
applicant within 20 business days of receipt of the completed request form and
payment of the $300 fee. The preapplication report produced by the utility is
nonbinding, it does not confer any rights, and the applicant must still
successfully apply to interconnect to the utility's system. The written
preapplication report request form shall include the following information to
clearly and sufficiently identify the location of the proposed point of
interconnection:
(1) Proposed distributed
generation facility owner's contact information, including name, address,
telephone number, and email address.
(2) Project location (street address with
nearby cross streets and name of town).
(3) Meter number, pole number, or other
equivalent information identifying the proposed point of interconnection, if
available.
(4) Generator type
(e.g., solar, wind, combined heat and power).
(5) Size (alternating current kW).
(6) Single or three-phase generator
configuration.
(7) Stand-alone
generator (whether or not there is an onsite load, not including station
service).
(8) Whether or not new
service is requested. If there is existing service, include the customer
account number, site minimum and maximum current or proposed electric loads in
kW (if available) and specify if the load is expected to change.
c. Using the information provided
in the preapplication report request form in paragraph
45.4(2)"b," the utility will identify the substation/area bus,
bank or circuit likely to serve the proposed point of interconnection. This
selection by the utility does not necessarily indicate, after application of
the screens or study or both, that this would be the circuit to which the
distributed generation facility ultimately will be connected or that
interconnection will occur. The applicant must request additional
preapplication reports if information about multiple points of interconnection
is requested. Subject to paragraph 45.4(2)"d" and other
confidentiality concerns identified by the utility, the preapplication report
will include the following information:
(1)
Total capacity (in MW) of substation/area bus, bank or circuit based on normal
or operating ratings likely to serve the proposed point of
interconnection.
(2) Existing
aggregate generation capacity (in MW) interconnected to a substation/area bus,
bank or circuit (i.e., amount of generation online) likely to serve the
proposed point of interconnection.
(3) Aggregate queued generation capacity (in
MW) for a substation/area bus, bank or circuit (i.e., amount of generation in
the queue) likely to serve the proposed point of interconnection.
(4) Available capacity (in MW) of
substation/area bus or bank and circuit likely to serve the proposed point of
interconnection (i.e., total capacity less the sum of existing aggregate
generation capacity and aggregate queued generation capacity).
(5) Substation nominal distribution voltage
or transmission nominal voltage or both if applicable.
(6) Nominal distribution circuit voltage at
the proposed point of interconnection.
(7) Approximate circuit distance between the
proposed point of interconnection and the substation.
(8) Actual or estimated peak load and minimum
load data, including daytime minimum load and absolute minimum load, when
applicable, for relevant line sections.
(9) Number and rating of protective devices
and number and type (standard, bi-directional) of voltage-regulating devices
between the proposed point of interconnection and the substation/area and
whether or not the substation has a load tap changer.
(10) Number of phases available at the
proposed point of interconnection. If it is a single phase, distance from the
three-phase circuit.
(11) Limiting
conductor ratings from the proposed point of interconnection to the
distribution substation.
(12)
Whether the point of interconnection is located on a spot network, grid
network, or radial supply.
(13)
Based on the proposed point of interconnection, existing or known constraints
such as, but not limited to, electrical dependencies at that location,
short-circuit interrupting capacity issues, power quality or stability issues
on the circuit, capacity constraints, or secondary networks.
d. The preapplication report need
only include existing data. A preapplication report request does not obligate
the utility to conduct a study or other analysis of the proposed generator in
the event that data is not readily available. If the utility cannot complete
all or some of the preapplication report due to lack of available data, the
utility shall provide the applicant with a preapplication report that includes
the data that is available. The provision of information on "available
capacity" pursuant to subparagraph 45.4(2)"c"(4) does not
imply that an interconnection up to this level may be completed without impacts
since there are many variables studied as part of the interconnection review
process and data provided in the preapplication report may become outdated at
the time of the submission of the complete interconnection request.
Notwithstanding any of the provisions of this subrule, the utility shall, in
good faith, include data in the preapplication report that represents the best
available information at the time of reporting.
(3) Utilities shall specify the fee by level
that the applicant shall remit to process the interconnection request. The fee
shall be specified in the interconnection request forms. The utilities shall
not charge more than the fees as specified below:
a. Level 1 - $125 application fee and up to
an additional $125 if the utility performs a witness test as specified in
subrule 45.5(10).
b. Level 2 - $250
application fee plus $1 per kVA and up to an additional $125 if the utility
performs a witness test as specified in subrule 45.5(10).
c. Level 3 - $500 application fee plus $2 per
kVA.
d. Level 4 - $1,000
application fee plus $2 per kVA.
(4) Interconnection requests may be submitted
electronically, if agreed to by the parties.