Iowa Code r. 567-120.9 - Landfarm operating requirements
All landfarms shall comply with the following operating requirements:
(1)
Standard
PCS. Only standard PCS may be land applied or stored at a landfarm
without a permit amendment from the department. A permit amendment from the
department, pursuant to subrule 120.4(10), shall be obtained for each
particular source and type of nonstandard PCS before that PCS may be land
applied or stored at a landfarm. The permit amendment application shall include
a justification of how the PCS can be safely and effectively remediated by
landfarming.
(2)
Saturated
or slurry PCS. PCS in a saturated or slurry condition shall not be
applied to the land or stored at a landfarm. PCS in such a condition shall be
bulked with other biodegradable materials (e.g., compost, mulch) until it is no
longer saturated or in a slurry before it is applied to the land or stored at a
landfarm.
(3)
PCS delivery
and storage. Only PCS that is from an emergency cleanup may be
delivered during the non-landfarm season. PCS delivered during non-landfarm
season may be stored as follows until the conditions of subrule 120.9(4) are
satisfied or within the first seven days of landfarm season, whichever is
shorter. PCS that cannot immediately be applied to the land at the landfarm
during landfarm season may be stored at the landfarm as follows.
a.
Seven days or less. PCS
may be stored up to seven days in compliance with the following requirements:
(1) Over an impervious surface (e.g., tarp,
concrete pad, plastic sheeting).
(2) Under a roof or tarp to minimize the
infiltration of precipitation.
(3)
In an area with minimal potential for stormwater run-on.
b.
Extended storage time. No
PCS shall be stored longer than seven days during landfarm season without
written permission from the department field office that has jurisdiction over
the landfarm.
(4)
PCS application weather and landfarm season.
a. PCS shall only be applied to the land
during non-landfarm season if the PCS must be applied to the land as part of an
emergency cleanup supervised by the department pursuant to subrule 120.6(1), or
all of the following conditions exist:
(1)
The landfarm plot is free of snow.
(2) The slope of the landfarm plot is less
than 3 percent.
(3) The PCS is
incorporated into the soil as soon as site conditions allow.
b. PCS shall not be applied to the
land during precipitation.
(5)
One application, source and type
of PCS per plot. One application of a particular source and type of
PCS may be applied to a landfarm plot. A landfarm may only apply a subsequent
application of PCS to a previously utilized landfarm plot if such application
is in compliance with the following:
a. The
plot has been tested pursuant to subparagraphs 120.6(2)"c"(1),
(2), and (3), and the results demonstrate that petroleum constituent
concentrations are less than 0.54 mg/kg for benzene, 42 mg/kg for toluene, 15
mg/kg for ethylbenzene, 3800 mg/kg for TEH-diesel, and 0.02 mg/kg for
MTBE.
b. A subsequent application
of a particular source and type of PCS may not be applied within 15 feet of an
area used as a single-use landfarm until the single-use landfarm is closed
pursuant to subrule 120.12(2).
(6)
PCS application rates.
PCS shall be land applied at a rate that is as uniform as practical over an
area sufficient to satisfy the greater of the following area requirements.
However, PCS from an emergency cleanup supervised by the department pursuant to
subrule 120.6(1) may instead be land applied at a rate of 162 ft2 of landfarm
area per cubic yard (yd3) of PCS, that is as uniform as practical, and in which
no layer of unincorporated PCS is thicker than 2 inches.
a.
Petroleum constituents.
PCS shall be land applied over the largest area required by the following:
(1) Benzene. PCS contaminated with benzene
shall be land applied in accordance with Table 1. The average concentration of
benzene in the PCS shall be used to determine the landfarm area (ft2) required
per cubic yard (yd3) of PCS to be land applied. The average concentration of
benzene shall be calculated from all soil boring test results that are within
the PCS excavation area. The application shall be as uniform as practical over
the area required.
|
Table 1 |
|||
|
Average concentration of benzene (mg/kg) |
Ft2 of landfarm area per yd3 of PCS applied |
Maximum thickness of unincorporated PCS |
Yd3 of PCS per acre of landfarm |
|
0< mg/kg <=10 |
81 ft2 |
4 inches |
537 yd3 |
|
10< mg/kg <=20 |
162 ft2 |
2 inches |
268 yd3 |
|
20< mg/kg |
324 ft2 |
1 inch |
134 yd3 |
(2)
Toluene, ethylbenzene, xylene, and TEH-diesel. PCS that is not contaminated
with benzene or MTBE, but is contaminated with toluene, ethylbenzene, xylene,
TEH-diesel, or some combination thereof, shall be land applied at a rate of 81
ft2 of landfarm area per cubic yard (yd3) of PCS. The application shall be as
uniform as practical, and no layer of unincorporated PCS shall be thicker than
4 inches.
b.
Total heavy metals. PCS that has been tested for heavy metals
pursuant to subparagraph 120.6(2)"c"(4) shall be applied at a
rate that is as uniform as practical, that results in no layer of PCS thicker
than 4 inches, and that upon incorporation produces a landfarm soil that
satisfies the following requirements. This analysis requires prior testing of
background levels of heavy metals at the proposed landfarm site.
(1) Total heavy metals are less than 2,500
milligrams per kilogram (mg/kg).
(2) Any particular concentration of a heavy
metal is less than the appropriate statewide standard for soil developed
pursuant to 567-Chapter 137.
(7)
Flagging. The landfarm
plot(s) upon which PCS is land applied shall be flagged for one year after land
application or until the landfarm is closed pursuant to rule
567-120.12 (455B), whichever is
shorter.
(8)
Removal of
solid waste and rubble. All solid waste that is not PCS (e.g., pipe)
shall be removed and properly disposed of. All rubble, stones, and debris
larger than 4 inches in diameter, or that interfere with incorporating and
turning the PCS, shall be removed and properly disposed of.
(9)
PCS incorporation. PCS
shall be incorporated into the soil by tilling, disking, or other suitable
means within 48 hours of being land applied or before the next precipitation
event, whichever is sooner. PCS shall not be incorporated deeper than 12
inches.
(10)
Turning the
PCS. After incorporation, the PCS shall be turned by tilling, disking,
or other suitable means at least once per month for the first three months
during landfarm season.
(11)
No crops for consumption. Landfarms shall not grow crops
within 15 feet of a landfarm plot that is flagged pursuant to subrule 120.9(7).
Crops for human and livestock consumption may be grown at a single-use landfarm
after the landfarm plot is no longer required to be flagged pursuant to subrule
120.9(7).
(12)
Removal of
PCS from a landfarm. PCS shall not be removed from a landfarm until
the landfarm is closed pursuant to rule
567-120.12 (455B) or the
following conditions are met:
a. One sample
from each 2,500 ft2 (e.g., 50-foot × 50-foot area) of landfarm plot is
analyzed pursuant to subparagraphs 120.6(2)"c"(1), (2), and
(3). A minimum of one sample per landfarm plot shall be obtained. All samples
shall be obtained from between the top 2 to 6 inches of soil.
b. The results of the tests in paragraph
120.12(2)"a" demonstrate that petroleum constituent
concentrations for benzene, toluene, ethylbenzene, TEH-diesel, and MTBE are
below the detection limits required by 567-Chapter 135.
c. Records of the lab results, amount of PCS
removed, and the exact final location of the PCS shall be maintained by the
landfarm.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.