Kan. Admin. Regs. § 11-4-10 - Notification of completion
(a) The sponsor of a construction project shall notify the
commission and the chief engineer when the project is completed and ready for
final certification by the chief engineer. The notification of completion shall
be submitted on a form supplied by the commission and shall include the
following:
(1) The date of completion of the project;
(2) an itemized list of all costs of construction, engineering,
surveys, geological investigations, inspections, and land acquisition; and
(3) a request for final payment of funds for the project.
(b) The sponsor of a renovation project shall notify the
commission when the project is completed. The notification of completion shall
be submitted on a form supplied by the commission and shall include the
following information:
(1) The date of completion of the project;
(2) an itemized list of all costs of restoration, engineering,
surveys, geological investigations, inspections, and land acquisition costs;
(3) a final bathymetric survey and a determination of the final
excavated volume; and
(4) a request for final payment.
(c) Final disbursement of the funds due from appropriated state
funds shall be made after receipt of final certification from the chief
engineer.