Kan. Admin. Regs. § 11-4-2 - Phase I letter of interest
(a) Each prospective sponsor of new construction shall submit a
phase I letter of interest to the commission to determine if the proposed
project will qualify for the program. The letter of interest shall be submitted
on a form furnished by the commission.
(b) In the phase I letter of interest for renovation of an
existing lake, the sponsor shall provide the commission with evidence that the
proposed project meets the following initial eligibility requirements:
(1) The lake shall currently provide local public water supply
benefits or be resonably expected to do so in the future.
(2) The dam impounding the lake shall not be considered
hydrologically inadequate or unsafe by the chief engineer.
(c) The phase I letter of interest shall be reviewed by the
commission, and the sponsor shall be notified in writing if the proposed
project qualifies for funding or does not qualify.