Kan. Admin. Regs. § 28-16-134 - Projects documents
(a) Each loan
applicant for a sewerage facility projects shall submit, for the secretary's
review and approval, the following documents:
(1) A completed loan application on
application forms furnished by the department;
(2) A facilities plan that establishes the
need for the project;
(3) Complete
design plans, specifications, and construction bidding documents, including
detailed cost estimates necessary for competitive bidding, and projected
construction and payment schedules;
(4) A plan of operation, including an overall
project completion schedule, annual operating cost projections for a minimum of
five years, a description of the financial management system, and projected
revenues to operate and maintain the entire facility. Revenue projections shall
also include the loan repayment obligations; and
(5) A facility operations manual, which shall
be submitted before 90% of the project is completed.
(b) Each loan applicant for a nonpoint source
pollution control management plan implementation or groundwater quality
protection project shall submit, for the secretary's review and approval, the
following documents:
(1) A completed loan
application on application forms furnished by the department;
(2) Planning documents or any assessment
which establishes the need for the project;
(3) Documents needed to plan the construction
of the project.
(4) A plan of
operation and maintenance to assure project performance for the design life of
the project; and
(5) A binding
assurance that adequate financial resources will be available for operation and
maintenance of the project during the life of the project.