Kan. Admin. Regs. § 28-16-60 - Development of draft permit
(a) Each
application and any other relevant facts shall be reviewed by the director to
determine one of the following:
(1) A permit
shall be issued allowing the discharge.
(2) A permit shall be issued providing for no
discharge.
(3) A permit shall not
be issued.
(b) If the
issuance of a permit is deemed advisable, the proposed permit conditions shall
be formulated by the director, including all of the following:
(1) Effluent limitations developed according
to the "Kansas implementation procedures: wastewater permitting";
(2) a schedule of compliance, including any
necessary interim dates;
(3) any
special conditions; and
(4) a
monitoring program, if appropriate.