Kan. Admin. Regs. § 28-45-30 - Brine pond decommissioning and abandonment
(a) Each permittee that wants to decommission
and abandon a brine pond shall submit a closure plan to the department at least
six months before decommissioning. Decommissioning shall not begin until the
secretary has issued approval.
(b)
Each permittee shall include at a minimum the following information in the
closure plan:
(1) The procedure for
deactivating the various brine lines associated with the facility;
(2) the procedures for conducting vertical
sampling of the soils beneath the brine pond liner, including the bottom of the
brine pond and the dikes;
(3) the
procedure to test the groundwater beneath and around the brine pond;
(4) the procedures for the remediation,
removal, or disposal of brine, accumulated sludge in the brine pond,
contaminated soils, and contaminated groundwater;
(5) a description regarding the proposed
maintenance, deactivation, conversion, or demolition of the brine pond
structure, including disposal of each brine pond liner; and
(6) the procedures addressing the plugging of
any water well or monitoring well associated with the brine pond.
(c) Each permittee shall submit a
final closure report within 90 days of decommissioning completion.