Kan. Admin. Regs. § 5-3-7 - Request for extension of time
(a) For
applications filed after May 1, 1978, any request for extension of time either
for completion of diversion works or for perfecting the appropriation shall be
submitted to the chief engineer before the expiration of the time allowed for
completing the diversion works or perfecting the appropriation. The request
shall be signed by the holder of the approval of application and permit to
proceed, by the owner of the land to be irrigated, by an authorized official of
a municipality, corporation or partnership, or by any other person that has a
recognized interest in the appropriation.
Failure to request an extension of time to perfect the appropriation within the time allowed shall limit the water appropriation right to the extent perfected in accordance with the terms, conditions, and limitations set forth in the approval of application.
(b) The request for an extension of time
either for completion of diversion works or for perfecting the appropriation
shall be accompanied by the statutorily required filing fee and shall include
the following information:
(1) The
application number;
(2) the date
by which the diversion works will be completed or the appropriation will be
perfected;
(3) the progress that
has been made toward completing the diversion works or perfecting the
appropriation;
(4) if for
irrigation, the number of acres of land to which water has been applied during
one calendar year;
(5) the reason
why the diversion works have not been completed or the appropriation has not
been perfected; and
(6) the plans
for completing the diversion works or perfecting the appropriation.