(a) Each
utility shall annually submit to the commission, by March 1, a report in a
format approved by the commission listing all net metered facilities connected
with the utility during the prior calendar year, pursuant to the act.
(b) Each report shall specify the following
information:
(1) Information by customer
type, including the following for each net metered facility:
(A) The type of generation resource in
operation;
(B) zip code of the net
metered facility;
(C) first year of
interconnection;
(D) any excess
kilowatt-hours that expired at the end of the prior calendar year;
(E) generator size; and
(F) number and type of meters; and
(2) the utility's system retail
peak in Kansas and total rated net metered generating capacity for all net
metered facilities connected with the utility's system in Kansas.