Kan. Admin. Regs. § 82-9-19 - Commission decision upon review of contract
(a) Within 30 days
after the date a proceeding is begun to review a contract upon the grounds
specified in 82-9-17(b), the commission shall decide whether the contract
violates the provisions of 49 U.S.C. Sec. 10713, as in effect on September 23,
1983. If the commission finds that a violation exists, it shall:
(1) disapprove the contract;
(2) in the case of agricultural contracts
where the commission finds unreasonable discrimination by a carrier, order the
carrier to provide rates and services substantially similar to the contract at
issue with any differences in terms and conditions that are justified by the
evidence; or
(3) allow the carrier
to cancel the contract.
(b) Approval date of contract. Each contract
shall be approved on the 30th day after the filing date of that contract. If
the commission does not institute a proceeding to review the contract, the
contract shall be considered "expressly approved" by the commission.
(c) If the commission institutes a proceeding
to review a contract, that contract shall be approved:
(1) on the date the commission approves the
contract, if the date of approval is 30 or more days after the filing date of
the contract;
(2) on the 30th day
after the filing date of the contract, if the commission approves the contract
prior to the 30th day after the filing date of the contract; or
(3) on the 60th day after the filing date of
a contract, if the commission fails to disapprove the contract.