01-669 C.M.R. ch. 21, § 9 - SKID TRAILS, YARDS, AND EQUIPMENT OPERATION
A.
APPLICABILITY. The
requirements of Section 9 apply to the construction, maintenance, and use of
skid trails and yards in shoreland areas. This section does not apply to
crossings of water bodies conducted in compliance with Section 11 of this
rule.
B.
STREAM
CHANNELS. Equipment used in timber harvesting and related activities
shall not use stream channels as travel routes except when:
1. surface waters are frozen and snow
covered; and,
2. the activity will
not result in any ground disturbance.
C.
DESIGN, CONSTRUCTION, AND
CLOSEOUT. Skid trails and yards must be designed and constructed to
prevent sediment and concentrated water runoff from entering a water body. Upon
termination of their use, skid trails and yards must be stabilized.
D.
SETBACKS
1. Except for crossings of stream channels or
freshwater wetlands, equipment used in timber harvesting and related
activities, including but not limited to the use of skid trails and yards, must
be operated to avoid the exposure of mineral soil within 25 feet of any water
body or wetland regulated by this rule. On slopes of 10 percent or greater, the
setback for equipment operation must be increased by 20 feet, plus an
additional 10 feet for each 5 percent increase in slope above 10 percent. These
requirements are presented in an alternative format in the slope table in
Section 12 of this rule.
2. The
provisions of this subsection apply only to a face sloping toward the water
body or freshwater or coastal wetland, provided, however, that no portion of
such exposed mineral soil on a back face is closer than 25 feet from the normal
high water line of a water body or upland edge of a freshwater or coastal
wetland. The setback requirements of this subsection shall not apply to skid
trail approaches to crossings of stream channels or freshwater
wetlands.
3. Where such setbacks
are impracticable, appropriate techniques shall be used to avoid sedimentation
of the water body or wetland. Such techniques may include the installation of
sump holes or settling basins, and/or the effective use of additional ditch
relief culverts and ditch water turnouts placed to avoid sedimentation of the
water body or wetland. If, despite such precautions, sedimentation or the
disruption of shoreline integrity occurs, such conditions must be
corrected.
E.
Exception. Timber harvesting and related activities in shoreland
areas of streams draining less than 300 acres and wetlands adjacent to such
streams may be conducted in a manner not in conformity with the setback
requirements of the foregoing subsections provided persons conducting such
activities take reasonable measures to avoid the disruption of shoreline
integrity, the occurrence of sedimentation of water, and the disturbance of
stream banks, stream channels, shorelines, and soil lying within ponds and
wetlands. If, despite such precautions, the disruption of shoreline integrity,
sedimentation of water, or the disturbance of stream banks, stream channels,
shorelines, and soil lying within ponds and wetlands occurs, such conditions
must be corrected.
NOTE: For guidance on reasonable measures, consult the Bureau publication, "Best Management Practices for Forestry: Protecting Maine's Water Quality" (2004). This publication is available from the Bureau and on the Bureau's website, www.maineforestservice.gov.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.