02-041 C.M.R. ch. 75, § 5 - Periodic Inspections of Low Pressure Boilers

1. Inspection Methods and Frequency. Before the initial inspection certificate expires, and annually thereafter, all low pressure boilers in the State must be inspected as follows:
A. An Inspector must perform one (1) annual certificate inspection, which must be an external inspection conducted while the boiler is in operation; and
B. When construction permits, an Inspector must perform an internal inspection every third year.
2. Report. An Inspector must submit to the director a report of each inspection performed pursuant to Section 5, Subsection 1 of this Chapter on a form approved by the director.