Before any pressure vessel is operated in the State of Maine, the owner of the pressure vessel must register the pressure vessel with the director and must obtain a current, valid inspection certificate for the pressure vessel.
Before a relocated pressure vessel is installed, the owner must petition the chief inspector for a variance in accordance with Chapter 71 of these rules for approval of the installation. The chief inspector must perform the initial inspection of a relocated pressure vessel. Regardless of the type of inspection completed, the chief inspector must determine that the pressure vessel's material thickness and conditions are appropriate for the design and intended operating conditions.