02-041 C.M.R. ch. 77, § 2 - Welded Repairs and Alterations
1. All welded
repairs and alterations to a boiler or a pressure vessel must be performed as
follows:
A. By an appropriate R Certificate
Holder; and
B. In accordance with
the applicable standards specified in Chapter 73, Section 1, Subsection 3 of
these rules. In those cases where it is not possible to complete welded repairs
and alterations in accordance with the applicable standards specified in
Chapter 73, Section 1, Subsection 3 of these rules, the chief inspector shall
be consulted.
2. All
alteration plans must be submitted to the chief inspector on a form approved by
the director at least thirty (30) days prior to the alteration. Emergency
situations will be handled on a case-by-case basis. If an emergency situation
makes it not practicable to submit alteration plans in advance, the chief
inspector must be notified.
3. The
R Certificate Holder performing a repair or alteration must submit legible
copies of the forms documenting the welded repair or alteration to the director
within sixty (60) days of completing the work.
4. Routine repairs shall be completed as
required in the NBIC as adopted by the director in Chapter 73, or any
equivalent standard as approved by the director.