16-642 C.M.R. ch. 2, § 8 - PROJECT COMPLETION
1. When the TPI is
notified that construction is complete, the TPI shall conduct a final
inspection and create a final inspection report.
2. If, based on the final inspection, the TPI
deems components of the project are in compliance with the MUBEC, the TPI shall
issue a Certificate of Completion. The Certificate of Completion shall note the
TPI's Area(s) of Certification and any other limitations.
3. The TPI shall also present the Certificate
of Completion to the municipality who shall acknowledge receipt. The
municipality is only acknowledging the work of the TPI and not assuming
responsibility for compliance.
4.
Municipality is required to accept the Certificate of Completion indicating the
work has been finished and shall provide acknowledgement to the applicant.
Acknowledgement shall act as Certificate of Occupancy in respect to the MUBEC
portion of the project.