16-642 C.M.R. ch. 2, § 8 - PROJECT COMPLETION

1. When the TPI is notified that construction is complete, the TPI shall conduct a final inspection and create a final inspection report.
2. If, based on the final inspection, the TPI deems components of the project are in compliance with the MUBEC, the TPI shall issue a Certificate of Completion. The Certificate of Completion shall note the TPI's Area(s) of Certification and any other limitations.
3. The TPI shall also present the Certificate of Completion to the municipality who shall acknowledge receipt. The municipality is only acknowledging the work of the TPI and not assuming responsibility for compliance.
4. Municipality is required to accept the Certificate of Completion indicating the work has been finished and shall provide acknowledgement to the applicant. Acknowledgement shall act as Certificate of Occupancy in respect to the MUBEC portion of the project.

Notes

16-642 C.M.R. ch. 2, § 8

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.