1.
Awarding
Construction Contracts . The Eligible Applicant shall be responsible for
assuring that all procedures and legal requirements are observed in advertising
for bids, Request for Qualifications, and Request for Proposals, and in
awarding the construction contract. The text of the construction contract shall
not vary from the text of the copy submitted to the Department. The Department
may approve the award of construction contracts using any of the four delivery
methods outlined below in Subsections F(1)(a)-(c).
(a) Design-Bid-Build (DBB) Contracts:
(i) A DBB Contract shall be competitively
bid;
(ii) Prior to advertising, the
Eligible Applicant shall submits to the
Department the Plans and Specifications approved in accordance with subsection
D(3) of this rule (relating to approval of Plans and Specifications);
and
(iii) Submittals for Contract
Award for DBB Contracts. Prior to contract award, the Eligible Applicant shall
submit for approval to the Department the following documents:
(AA) A tabulation of all bids received and an
explanation for any rejected bids or otherwise disqualified bidders;
(BB) The proposed low bid proposal;
(CC) A certification that all required
acquisitions, leases, easements, right-of-way, relocations, (both voluntary and
involuntary) have been obtained for the Project to be built;
(DD) Documentation of MBE/WBE efforts by the
proposed low bid contractor, if applicable;
(EE) A notice of intent to award;
(FF) Evidence of public advertising;
and
(GG) A Project
budget.
(b)
Construction Management At-Risk (CMAR) and Progressive Design-Build (PDB)
Contracts (Phase 1 and Phase 2) (This section applies to both delivery
methods):
(i) Phase 1: CMAR and PDB Selection
Phase:
(AA) The CMAR firm or the PDB firm is
selected through a Qualifications Based Selection (QBS) process;
(BB) Prior to advertising for the Request For
Qualifications (RFQ), the Eligible Applicant shall submit for approval to the
Department:
(i) For PDB: A preliminary scope
of work for the PDB firm and a detailed description of the Project goals and
objectives; or
(ii) For CMAR: Plans
and Specifications (generally not more than 10-30% complete) in accordance with
subsection D(3); and
(iii) The
RFQ.
(CC) Submittals for
Award of Construction Management At-Risk and Progressive Design-Build
Contracts. Prior to contract award, the Eligible Applicant shall submit for
approval to the Department the following documents:
(i) A certification that all required
acquisitions, leases, easements, right-of-way, relocations, (both voluntary and
involuntary) have been obtained for the Project to be built;
(ii) A tabulation of the firms that responded
to the RFQ and the Eligible Applicant's scoring of them in the evaluation
process;
(iii) The selected firm's
proposal;
(iv) A notice of intent
to award;
(v) Evidence of public
advertising; and
(vi) A Project
budget.
(ii)
Phase 2: Construction Phase
(AA) Construction
trade subcontracted packages are competitively bid by subcontractors (typically
pre-qualified). The contracted CMAR or PDB firm may bid on trade
packages;
(BB) Prior to advertising
of construction trade subcontract packages, the Eligible Applicant shall
submits to the Department the Plans and
Specifications (generally not more than 60% complete) approved in accordance
with subsection D(3) of this rule (relating to approval of Plans and
Specifications); and
(CC)
Submittals for Award of Phase 2 CMAR or PDB Contract (or Contract Amendment).
Prior to contract (or contract amendment) award, the Eligible Applicant shall
submit for approval to the Department the following items;
(i) A tabulation of all construction trade
subcontract proposals received and an explanation for any rejected proposals or
otherwise disqualified bidders;
(ii) A notice of intent to award;
(iii) Evidence of public advertising;
and
(iv) A Project
budget.
(DD) Prior to
each phase of the construction, the Eligible Applicant shall submit to the
Department the final Plans and Specifications, upon completion by the PDB firm
or the engineer of record for a CMAR Project.
(EE) During the construction phase, the
selected CMAR or PDB firm will document its MBE/WBE efforts and submit its
compliance plan to the Department for approval.
(FF) The Eligible Applicant shall submit for
approval to the Department the firm fixed price or if applicable, all CMAR
guaranteed maximum price proposals.
(c) Fixed Price Design-Build (FPDB)
Contracts:
(i) The Fixed Price Design-Build
firm is selected through a Request for Proposal (RFP) process. This may be
conducted in either a single step (combined RFQ/RFP) or a two-step process
where a RFQ is used to pre-qualify firms for proposals;
(ii) Prior to advertising for the RFP, the
Eligible Applicant shall submit for approval to the Department:
(AA) Preliminary Plans and Specifications
(generally not more than 10-30% complete) in accordance with subsection D(3);
and
(BB) The RFP, which must
contain a cost component. The weight of the cost component in the evaluation
process is specific to the Project and is established by the Eligible
Applicant.
(iii)
Submittals for Contract Award for FPDB contract. Prior to contract award, the
Eligible Applicant shall submit for approval to the Department the following
documents:
(AA) A certification that all
required acquisitions, leases, easements, right-of-way, relocations, (both
voluntary and involuntary) have been obtained for the Project to be
built;
(BB) A tabulation of the
firms that responded to the RFP and the Eligible Applicant's scoring for them
in the evaluation process;
(CC) The
selected firm's proposal;
(DD) A
notice of intent to award;
(EE)
Evidence of public advertising; and
(FF) A Project budget.
(iv) Prior to each phase of the construction,
the Eligible Applicant shall submit to the Department the final Plans and
Specifications, upon completion by the FPDB firm.
(v) During the Construction Phase, the
selected FPDB firm will document its MBE/WBE efforts and submit its compliance
plan to the Department for approval.
(d) Executed Documents. Within 15 days of
contract signing, the Eligible Applicant shall submit to the Department a copy
of the executed documents containing the executed contract agreement, executed
bonds, insurance certificates, act of assurance, wage rates, notice to proceed
and any other documents required by subsection D(2) of this Chapter (relating
to Plans and Specifications).
2.
Force Account and Non-Competitive
Procurement
(a) Force Account. All
significant elements of the Project will be performed with skilled personnel
hired through one of the four construction delivery methods, F(1)(a)-(c).
However, the Department may approve the use of Force Account for design,
inspection and/or construction when the Eligible Applicant demonstrates that it
possesses the necessary competence required to accomplish such work and that
the work can be accomplished more economically by the use of the Force Account
method, or emergency circumstances dictate its use.
(b) Competitive Bidding will not be required
for direct Eligible Applicant purchases for proprietary equipment and for sole
source procurement with prior Department approval. The Eligible Applicant must
justify the purchase of proprietary equipment and demonstrate a compelling need
for sole source procurement, such as matching existing equipment, to obtain
Department approval.
3.
Inspection During Construction .After the construction contract is
awarded, the Eligible Applicant shall provide for adequate inspection of the
Project and require his/her assurance that the work is being performed in a
satisfactory manner in accordance with the approved Plans and Specifications,
approved alterations, and in accordance with sound engineering principles and
building practices. The Department is authorized to inspect the Project at any
time during construction in order to assure that Plans and Specifications are
being followed and that the Project is being built in accordance with sound
engineering principles and building practices. Such inspection, however, shall
never subject the State of Maine to any liability or action for damages. The
Department shall notify the Eligible Applicant and the Project Engineer of any
variances from the approved Plans and Specifications. Upon notification, the
Eligible Applicant and the Project Engineer shall immediately initiate any
necessary corrective action.
4.
Audits .The Department is authorized to and may conduct
engineering audits. The Bank is authorized to and may conduct financial and
program audits of every Project that is financed in whole or in part by SRF
funds. Each recipient of Financial Assistance from the Bank shall provide the
Bank with annual audited financial statements prepared by a professional
accountant or accounting firm. For purposes of this section, the following
definitions are applicable:
(a) Financial
audit. A review of all files for historical background for the Project, a visit
to the Project offices or site to gather sufficient information to perform a
detailed review of documents which substantiate the Project expense, a
tabulation of expenses, and the issuance of an audit report establishing that
expenses financed from the fund are or are not in conformance with terms and
provisions of loan documents.
(b)
Engineering audit. A physical inspection of the Project to analyze the Project
and compare it with the approved Plans and Specifications, and the issuance of
an inspection report which finds the Project in compliance with the Plans and
Specifications or which outlines any variances from the construction contract
and approved Plans and Specifications and which recommends corrective
action.
(c) Program audit. A review
of all files and records to determine and ensure compliance with Title VI of
the FWPCA in order to be eligible for and comply with the terms of any
Financial Assistance provided by the Bank.
5.
Alterations in Approved Plans and
Specifications .If, after the Department approves the Plans and
Specifications, it becomes apparent that changes are necessary, a change order
and justification must be submitted to the Department for review and approval.
Any change in previously approved Plans and Specifications may not alter the
basic purpose or effect of a Project. When possible, such a change order must
be submitted well in advance of the proposed alteration. The Department must
receive a written copy of all change orders. If there is immediate danger to
life or property, tentative approval of change orders may be secured via
telephone and confirmed by letter. A request for a change order should contain
sufficient information, including plans or drawings and cost estimates for
review of the proposal. After approval of the proposed alterations, copies of
the approved change order must be forwarded to the Project Engineer. If a
proposed change order would exceed 50% of the cost of the original contract,
the work must be put out to bid as a separate contract.
6.
Contractor Bankruptcy .In the
event of a contractor bankruptcy, any agreements regarding any settlement
proposed to be entered into with the bonding company (other than a bonding
company serving as general contractor or fully bonding another contractor
acting as their agent) must be submitted for approval by the Department. All
Project contractors must be bonded. The Eligible Applicant is responsible for
assuring that all procedural and legal requirements are observed in advertising
for bids and awarding a construction contract.
7.
Building Phase Submittals
.During the building phase of the Project, the Eligible Applicant shall submit
or perform the following:
(a) User Charge
System and Sewer Use Ordinance. Prior to placing a Treatment Works into
operation, if applicable, the Eligible Applicant shall adopt its user charge
system and sewer use ordinance and submit a copy of each for the Department's
approval. Further, the loan recipient shall implement the user charge system
for the useful life of the Project;
(b) Operation and Maintenance Manual. For new
Treatment Works or major upgrades, a final operation and maintenance manual
will be submitted for the Department's approval prior to placing the Treatment
Works or major upgrades into operation;
(c) As Built Drawings. A complete set of
as-built drawings will be submitted to the owner upon completion of all
construction;
(d) Substantial
Completion and Initiation of Operation Dates. Certificates of Substantial
Completion and notification of Initiation of Operation dates shall be submitted
to the Department upon completion of Project construction; and
(e) Other Submittals. Any other Building
phase submittals required as part of the loan documents shall be submitted to
the Department for its approval.
8.
Progress Payments
.Disbursements from the Construction Fund established by the Bank require
approval by the Department and the Bank. Certified requests for payment may be
submitted monthly, or less frequently for small contracts, on forms provided by
the Department. Upon approval by the Department, the request will be forwarded
to the Bank to authorize progress payments from the SRF Construction Fund for
the Project and in turn to the designated account established by the
applicant.
9.
Retainage .Prior to Substantial Completion, progress payments will
be made in an amount equal to the percentage indicated below but, in each case,
less the aggregate of payments previously made and less such amounts as the
Project Engineer may determine or the Eligible Applicant may withhold,
including but not limited to liquidated damages:
(a) 95 percent of work completed (with the
balance being retainage); and
(b)
95 percent of cost of materials and equipment not incorporated in the work
(with the balance being retainage).
Upon Substantial Completion, the Eligible Applicant shall
pay an amount sufficient to increase total payments to the contractor to 98
percent of the work completed, less such amounts as the Project Engineer shall
determine in accordance with the specifications. The remaining 2 percent
retainage may be held for one year after Substantial Completion and retained by
the Bank. This provision may be waived on Projects co-funded with other funding
agencies whose retainage policies conflict, on Projects with interim financing
or refinancing, or on a case by case basis when the Eligible Applicant presents
a compelling case against this provision.
10.
Claims or Disputes .All
claims or disputes between the owner and the contractor must be settled in
accordance with general and supplementary conditions required by the Department
and made part of the Plans and Specifications.
11.
Documents .All documents
provided to either the Bank or the Department must be available to both the
Bank and the Department.