Md. Code Regs. 26.16.05.05 - MDE 330 Certificate
A.
Inspections performed under this chapter to satisfy the Maryland Reduction of
Lead Risk in Housing Act requirements shall be documented on MDE 330
certificates and supporting forms according to procedures established by the
Department . MDE 330 forms may not be used for any other purpose.
B. All results of passing inspections shall
be submitted to the Department within 10 days of performing a visual
inspection, or within 10 days of obtaining laboratory analysis of dust
samples.
C. All results of failing
inspections shall be submitted to the Department within 30 days of performing a
visual inspection, or within 30 days of obtaining laboratory analysis of dust
samples.