310 CMR, § 40.0875 - As-built Construction Report
(1)
As-built Construction plans shall be prepared and submitted to the Department
in an As-built Construction Report for:
(a)
any disposal site where an Engineered Barrier, cap or other on-site system for
the containment and/or physical immobilization of oil and/or hazardous material
is constructed as part of the Remedial Action Alternative; or
(b) any disposal site where the Comprehensive
Remedial Alternative as actually constructed varies significantly from the
description of the alternative provided in the RIP under
310
CMR 40.0874.
(2) The As-built Construction Report shall
include, without limitation, the following information:
(a) construction activities conducted, and
techniques and materials used;
(b)
tests and measurements performed;
(c) any significant modifications of the
design or construction of the selected Comprehensive Remedial Alternative as
described under
310
CMR 40.0874(3)(c) of the
RIP; and
(d) as built
drawings.
(3) As-built
plans for the Comprehensive Remedial Action shall be prepared in conformance
with appropriate engineering and construction standards and practices, and
regulations applicable to construction plans and activities.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.