700 CMR, § 14.03 - Aggregate Bonding Capacity and Single Contract Limits for Contractors
(1)
Aggregate and Single Bonding Capacity. The
Prequalification Committee shall verify the Contractor's Aggregate Bonding
Capacity and Single Bonding Capacity, as is evidenced by a letter from the
Surety's authorized representative in accordance with 700 CMR 14.02(8).
Unlimited Aggregate Bonding Capacities shall not be allowed.
(2)
Classes of Work.
The Prequalification Committee may prequalify Contractors in one or more of the
classes of work. The Classes of Work established by the Prequalification
Committee, and the definitions of and/or the prequalification requirements of
such Classes of Work, may be amended by the Prequalification Committee from
time to time. The Prequalification Committee may also establish additional
Classes of Work for specialized contracts. Contractors will be notified of such
special Classes of Work in the Notice to Contractors, Advertisement for Bids,
or Instructions to Proposers for the particular project, and may apply for
Prequalification in such special Classes of Work in accordance with 700 CMR
14.02(9)
(3)
Single
Contract Limit. The Prequalification Committee may establish a
Single Contract Limit for the Contractor in any Classes of Work for which the
Contractor has been Prequalified. A Single Contract Limit may be established,
if, in the opinion of the Prequalification Committee, the Contractor does not
have adequate experience, responsibility, competency, or equipment necessary to
undertake an individual contract valued at the Contractor's Single Bonding
Capacity within that Class of Work. In establishing Single Contract Limits, the
Prequalification Committee shall consider, but shall not be limited to
considering, the Contractor's competency and responsibility, the amount and
condition of its equipment, the experience of its principal or key personnel,
its history of payment to subcontractors and material suppliers, and previous
work experience.
(4)
Duration of Prequalification Status. Prequalification
certification shall remain in effect for a duration of time stipulated in the
Prequalification Certificate with a maximum of 12 months as indicated in the
Prequalification Certificate.
(a) The
Prequalification Committee may revise the duration of a Contactor's
Prequalification Status at any time.
(b) If a material change has occurred in the
Contractor's bonding capacity surety, or financial condition, or if the
Contractor has undergone any change in the name or structure of the firm, its
officers, or ownership, written notice shall be given to the Prequalification
Committee by the Contractor, whereupon a new Application for Prequalification
or a letter verifying Contractor's Aggregate and Single Bonding Capacity shall
be required and the Contractor's Prequalification status and Single Contract
Limit(s) may be revised. Should the Aggregate or Single Bonding capacity of a
Contractor change, a letter from the surety stating this fact must be submitted
to the Prequalification Committee.
(c) The Prequalification Committee may at any
time request, in writing, that the Contractor furnish additional information
relative to its Prequalification status and Single Contract Limit(s). Such
request shall set forth the reason such information is required. If the
requested information is not filed within 30 days from date of such request,
the Contractor's Prequalification Certificate may be revoked, and, if revoked,
bids from the Contractor shall not be accepted.
(d) Requests by Contractors for the revision
of Aggregate and Single Bonding Capacity, Single Contract Limits or for
additional classes of work may be considered by the Prequalification Committee
at any time. Unless otherwise approved by the Prequalification Committee, such
requests must be submitted at least 21 calendar days prior to a bid opening in
order to receive consideration for that bid opening.
(e) A Prequalification Certificate may be
modified based on one or more of the reasons set forth in 700 CMR 14.06(1) and
14.06(3), or based on evaluations of the quality of the Contractor's
performance by the Department or Other Awarding Authority, whether as a general
contractor or subcontractor. The Department may establish procedures and forms
to be used by the Department and Other Awarding Authorities to evaluate the
Contractor's performance.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.