780 CMR, CHAPTER 1, PART 2, SECTION 105, 105.5 - Expiration

Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 180 days after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work is commenced. The building official is authorized to grant, in writing, one or more extensions of time, for periods not more than 180 days each. The extension shall be requested in writing prior to the 180 day expiration date and justifiable cause demonstrated.

Notes

780 CMR, CHAPTER 1, PART 2, SECTION 105, 105.5
Amended by Mass Register Issue 1532, eff. 10/11/2024.