Mich. Admin. Code R. 29.5654 - Permits
Rule 654. Section 1.8 of the FL/CL code is adopted with the following changes and sections 1.8.1, 1.8.2, 1.8.3, 1.8.4, and 1.8.5 are added to the FL/CL code as follows: 1.8 Permits.
1.8.1 For installations, where individual
storage capacity is more than 1,100 gallons (4,180 liters), an owner or owners
designee shall submit an application for plan review to the bureau not less
than 30 days before the installation of an aboveground storage tank system.
Tanks with storage capacity of 1,100 gallons or less shall comply with these
rules but are not required to submit an application for plan review and are not
required to be certified.
1.8.2 The
installation application shall include a plot map that shows all of the
following information:
(a) The locations of
buildings, public roadways, railroad mainlines, and power lines.
(b) Storm sewers, sanitary sewers, manholes,
and catch basins.
(c) The proposed
locations of tanks and buildings.
(d) The location of property lines.
(e) The location of existing tanks,
aboveground and underground, within 50 feet (15 meters) of the
installation.
(f) The material of
construction, the dimension, and the capacity of each tank.
(g) The class of liquid stored.
(h) The type of venting and pressure
relief.
(i) The method of spill
control provided.
1.8.3
The bureau shall issue a plan review report within 30 days of the receipt. If
the report is not issued within 30 days, the installation may be constructed
according to the submitted plans and comply with these rules.
1.8.4 Upon completion of the installation,
the owner or designee shall notify the bureau not fewer than 7 calendar days
before the installation is placed in service. The bureau shall inspect the
installation following the receipt of notification and shall certify the
installation if the requirements of these rules have been met. If the
inspection is not made within 7 calendar days of receipt of notification, the
installation may be placed in service and a notarized affidavit shall be
submitted to the bureau attesting to the fact that the installation complies
with the plans submitted and applicable rules.
1.8.5 Upon request, all plans and
specifications that are submitted to the bureau for review shall be returned
after the bureau has certified the installation or within 30 working days after
notification to the authority having jurisdiction of the completion of the
installation. Plans and specifications may be marked "confidential do not copy"
when they are submitted.