Mich. Admin. Code R. 324.606 - Production tests for newly completed or change of status wells subject to proration
Rule 606. A permittee of a well shall conduct production tests, not to exceed the prorated allowable, on a newly completed well. On a previously tested well, when a change of well status or the stimulation of the well may have resulted in changes in producing capacity, the tests shall be commenced within 10 days after well completion, change of well status, or production stimulation treatments. A permittee shall report the results of all production tests to the supervisor or authorized representative of the supervisor within 30 days after completion of the tests and shall certify the results on forms prescribed by the supervisor.