Mich. Admin. Code R. 408.15732 - Guylines and hoisting lines
Rule 5732.
(1)
A guyline shall be maintained in good condition and shall be of a strength,
including auxiliary devices such as chains, boomers, and clamps, capable of
withstanding loads for the anticipated service conditions. A guyline shall have
a safety factor of 3.
(2) Each
guyline shall be visually inspected before each rig up. A guyline shall be
removed from service and replaced if in any length of 10 diameters the total
number of visible broken wires exceeds 10% of the total number of wires in the
line or if the guyline shows other signs of excessive wear, corrosion, or
defect.
(3) Wire rope used for
hoisting purposes shall be of a strength to safely lift and otherwise handle
anticipated loads under conditions of service. The maximum allowable hoisting
line working load shall be based on a minimum safety factor of 3 for normal
operations. A minimum safety factor of 2 is allowed when setting casing,
pulling on stuck pipe, or while engaging in similar infrequent
operations.
(4) A damaged portion
of a hoisting line shall be removed from service when any of the following
conditions exist:
(a) Three broken wires are
found in 1 lay of 6 by 6 wire rope.
(b) Six broken wires are found in 1 lay of 6
by 19 wire rope.
(c) Eight broken
wires are found in 1 lay of 8 by 19 wire rope.
(d) Nine broken wires are found in 1 lay of 6
by 37 wire rope.
(e) Wire ropes not
covered in this subrule are found to have 4% or more of the total number of
wires composing such rope broken in 1 lay.
(f) Marked corrosion appears.
(g) Corroded or broken wires are noted at end
connections.
(h) End connections
are corroded, cracked, bent, worn, or improperly applied.
(i) Evidence is noted of kinking, crushing,
cutting, or unstranding.
(5) When the hoisting line is placed on the
hoisting drum, the end shall be securely fastened and there shall be not less
than 7 line wraps remaining on the drum at the lowest operating position of the
traveling block.
(6) A deadline
anchor for a hoisting line shall be so constructed, installed, and maintained
that its strength equals or exceeds the working strength of the hoisting
line.
(7) When a ton-mile
calculation indicates, or an inspection reveals, that the hoisting line safety
factor has been materially reduced, the line shall be slipped, cut, or
replaced.
(8) A hoisting line under
load shall not be allowed to come in contact with any part of the derrick or
mast, stationary equipment, or material in the structure, except at the crown
block sheaves, traveling block sheaves, a turnback roller, and a line
stabilizer, when needed.
(9) The
hoisting line shall not be removed from the hoisting drum until the traveling
block is rested on the rig floor or held suspended by a separate wire rope or
chain.