Mich. Admin. Code R. 408.30509 - [Rescinded effective 8/29/2025] Frame and masonry inspection
Rule 509. Section R109.1.4 of the code is amended to read as follows:
R109.1.4. Frame and masonry
inspection. Inspection of framing construction shall be made after the roof,
all framing, firestopping, draftstopping, and bracing are in place and after
the plumbing, mechanical, and electrical rough inspections are approved.
Masonry inspections shall be made after the completed installation of base
course flashing as specified in section R703.7.5 of the code and
water-resistive barrier as specified in section R703.2 of the code and after
the masonry construction is completed.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
Rule 509. Section R109.1.4 of the
R109.1.4. Frame and masonry inspection . Inspection of framing construction shall be made after the roof, all framing, firestopping, draftstopping, and bracing are in place and after the plumbing, mechanical, and electrical rough inspections are approved . Masonry inspections shall be made after the completed installation of base course flashing as specified in section R703.7.5 of the code and water-resistive barrier as specified in section R703.2 of the code and after the masonry construction is completed.