Mich. Admin. Code R. 460.938 - Public interconnection list
Rule 38.
(1) An
electric utility shall maintain a publicly available interconnection list,
which is available in a sortable spreadsheet format. The sortable spreadsheet
must be provided to the public upon request. An electric utility that has
received not less than 100 complete interconnection applications in a year
shall publish this list on the electric utility's website. The public
interconnection list must be updated monthly. If no changes to the spreadsheet
have occurred in that month, a note to that effect must be clearly indicated on
the spreadsheet. The date of the most recent update must be clearly
indicated.
(2) The public
interconnection list must include all of the following:
(a) An application identifier.
(b) The date that the electric utility
received the application.
(c) The
date that the electric utility considered the application to be complete and
conforming.
(d) Whether the
application is on the non-export track, fast track, or study track.
(e) The proposed DER nameplate
rating.
(f) The proposed DER
interconnection size level.
(g) The
DER technology type.
(h) The county
and township in which the proposed point of common coupling will be
located.
(i) The current status of
the application's progress in the interconnection process.
(j) The labels, names, or identifiers of the
distribution circuit and substation.
Notes