Mich. Admin. Code R. 460.958 - Scoping meeting for interconnection applications that are to be studied individually
Rule 58.
(1) This
rule applies only to interconnection applications proceeding pursuant to an
individual study agreement.
(2) Upon
request of the applicant, the electric utility and the applicant shall schedule
a scoping meeting between the electric utility and the applicant to discuss the
interconnection application and review existing fast track results, if any. The
scoping meeting must take place within 20 business days after the
interconnection application is considered complete by the electric utility or,
if applicable, the fast track has been completed and the applicant has elected
to continue with the system impact study or facilities study.
(3) Scoping meetings are limited to 1 hour
per application. Multiple applications by the same applicant may be addressed
in the same meeting.
(4) The scoping
meeting may occur in-person or via telecommunications.
(5) During the scoping meeting, the electric
utility shall identify and communicate to the applicant whether the applicant
must proceed to a system impact study, a facilities study, or an
interconnection agreement and the basis for that decision, and 1 of the
following must occur:
(a) If a system impact
study must be performed, the interconnection application proceeds to
R 460.960.
(b) If a facilities study must be performed,
the interconnection application proceeds to
R 460.962.
(c) If a system impact study is not required
and a facilities study is not required, the interconnection application must
proceed to R 460.964 for an interconnection
agreement.
Notes
State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.
No prior version found.