Mich. Admin. Code R. 460.968 - Authorization required prior to parallel operation
Rule 68.
(1) The
electric utility shall provide to the applicant written authorization to
operate in parallel with the electric utility within 5 business days of all of
the following conditions being met:
(a) The
electric utility notified the interconnection applicant that the commissioning
test and inspection, where applicable, are accepted.
(b) The applicant has executed a standard
level 1, 2, and 3 interconnection agreement or level 4 and 5 interconnection
agreement and complied with all applicable parallel operation requirements as
set forth in the electric utility's interconnection procedures and applicable
interconnection agreement.
(c) The
applicant complied with all applicable local, state, and federal
requirements.
(d) The electric
utility received full payments for all outstanding bills.
(2) With the written authorization,
interconnection of the DER is considered approved for parallel operation, the
DER may begin operating, and the applicant is considered an interconnection
customer.
(3) The applicant shall
not operate its DER in parallel with the electric utility's distribution system
without prior written permission to operate from the electric
utility.
(4) Subject to reasonable
timing and other conditions, including completion of conditions in the
interconnection agreement or interconnection procedures, the electric utility
shall allow for reasonable but limited testing before written authorization has
occurred.