Subp. 4.
Decommissioning.
A. Within 60
days of any of the occurrences under item B, a licensee must provide
notification to the commissioner in writing of such occurrence and:
(1) begin decommissioning the licensee's site
or any separate building or outdoor area that contains residual radioactivity
so that the building or outdoor area is suitable for release according to this
chapter; or
(2) submit within 12
months of notification a decommissioning plan, if required under item E or F,
and begin decommissioning upon approval of that plan.
B. Notice under item A is required when:
(1) the license has expired under subpart 1
or 2;
(2) the licensee has decided
to permanently cease principal activities at the entire site or in any separate
building or outdoor area;
(3) no
principal activities have been conducted under the license for a period of 24
months; or
(4) no principal
activities have been conducted for a period of 24 months in any separate
building or outdoor area that contains residual radioactivity such that the
building or outdoor area is unsuitable for release according to this
chapter.
C. Coincident
with the notification required under item A, the licensee must maintain in
effect all decommissioning financial assurances established by the licensee
under part 4731.0780 in conjunction with license issuance or renewal or as
required under this part. The amount of the financial assurance must be
increased, or may be decreased, as appropriate, to cover the detailed cost
estimate for decommissioning established under item H, subitem (5). Following
approval of the decommissioning plan, a licensee may reduce the amount of the
financial assurance as decommissioning proceeds and radiological contamination
is reduced at the site with the approval of the commissioner.
D. The commissioner may grant a request to
delay or postpone initiation of the decommissioning process if the commissioner
determines that this relief is not detrimental to the public health and safety
and is otherwise in the public interest. The request must be submitted no later
than 30 days before notification under item A. The schedule for decommissioning
in this subpart may not commence until the commissioner has made a
determination on the request.
E. A
decommissioning plan must be submitted if:
(1) required by a license condition;
or
(2) the procedures and
activities necessary to carry out decommissioning of the site or separate
building or outdoor area have not been previously approved by the commissioner
and the procedures could increase potential health and safety impacts to
workers or the public, such as in any of the following cases:
(a) procedures would involve techniques not
routinely applied during cleanup and maintenance operations;
(b) workers would be entering areas not
normally occupied where surface contamination and radiation levels are
significantly higher than routinely encountered during operation;
(c) procedures could result in significantly
greater airborne concentrations of radioactive materials than are present
during operation; or
(d) procedures
could result in significantly greater releases of radioactive material to the
environment than those associated with operation.
F. The commissioner may approve an
alternate schedule for submittal of a decommissioning plan required under this
subpart if the commissioner determines that the alternative schedule is
necessary to the effective conduct of decommissioning operations and presents
no undue risk from the radiation to the public health and safety and is
otherwise in the public interest.
G. The procedures under item E, subitem (2),
may not be performed before approval of the decommissioning plan.
H. The proposed decommissioning plan for the
site or separate building or outdoor area must include:
(1) a description of the conditions of the
site or separate building or outdoor area sufficient to evaluate the
acceptability of the plan;
(2) a
description of planned decommissioning activities;
(3) a description of the methods used to
ensure protection of workers and the environment against radiation hazards
during decommissioning;
(4) a
description of the planned final radiation survey;
(5) an updated detailed cost estimate for
decommissioning, comparison of that estimate with present funds set aside for
decommissioning, and a plan for ensuring the availability of adequate funds for
completion of decommissioning; and
(6) for decommissioning plans calling for
completion of decommissioning later than 24 months after plan approval, a
justification for the delay based on the criteria in item K.
I. The commissioner shall approve
a proposed decommissioning plan if the information in the plan demonstrates
that the decommissioning will be completed as soon as practicable and that the
health and safety of workers and the public will be adequately
protected.
J. Except as provided in
item K, a licensee must:
(1) complete
decommissioning of the site or separate building or outdoor area as soon as
practicable but no later than 24 months following the initiation of
decommissioning; and
(2) request
license termination as soon as practicable but no later than 24 months
following the initiation of decommissioning, when decommissioning involves the
entire site.
K. The
commissioner may approve a request for an alternative schedule for completion
of decommissioning of the site or separate building or outdoor area, and
license termination if appropriate, if the commissioner determines that the
alternative is warranted by consideration of:
(1) whether it is technically feasible to
complete decommissioning within the allotted 24-month period;
(2) whether sufficient waste disposal
capacity is available to allow completion of decommissioning within the
allotted 24-month period;
(3)
whether a significant volume reduction in wastes requiring disposal will be
achieved by allowing short-lived radionuclides to decay;
(4) whether a significant reduction in
radiation exposure to workers can be achieved by allowing short-lived
radionuclides to decay; and
(5)
other site-specific factors that the commissioner may consider appropriate on a
case-by-case basis, such as the regulatory requirements of other governmental
agencies, lawsuits, groundwater treatment activities, monitored natural
groundwater restoration, actions that could result in more environmental harm
than deferring clean up, and other factors beyond the control of the
licensee.
L. As the
final step in decommissioning, the licensee must:
(1) certify the disposition of all licensed
material, including accumulated wastes, by submitting a completed NRC Form 314
or equivalent information; and
(2)
conduct a radiation survey of the premises where the licensed activities were
carried out and submit a report of the results of the survey, unless the
licensee demonstrates in some other manner that the premises are suitable for
release according to part 4731.2100. The licensee must, as appropriate:
(a) for gamma radiation, report levels of
radiation in units of microroentgens (millisieverts) per hour at one meter from
surfaces;
(b) for radioactivity,
including alpha and beta radiation, report levels of radiation in units of
disintegrations per minute or microcuries (megabecquerels) per 100 square
centimeters removable and fixed for surfaces, microcuries (megabecquerels) per
milliliter for water, and picocuries (becquerels) per gram for solids such as
soils or concrete; and
(c) specify
the survey instruments used and certify that each instrument is properly
calibrated and tested.
M. Specific licenses, including expired
licenses, shall be terminated by written notice to the licensee when the
commissioner determines that:
(1) source
material has been properly disposed of;
(2) reasonable effort has been made to
eliminate residual radioactive contamination, if present;
(3) a radiation survey has been performed
that demonstrates, or other information submitted by the licensee is sufficient
to demonstrate, that the premises are suitable for release according to part
4731.2100; and
(4) records required
under part 4731.0825, subparts 4 and 6, have been received.