Minn. R. agency 138, ch. 7854, pt. 7854.1200 - DELAY IN CONSTRUCTION

If the permittee has not commenced construction of the project within two years after issuance of the site permit, the permittee must advise the commission of the reasons construction has not commenced. In such event, the commission may determine whether the permit should be revoked. No revocation of a permit for failure to commence construction may be undertaken except in accordance with part 7854.1300, subpart 4.

Notes

Minn. R. agency 138, ch. 7854, pt. 7854.1200
26 SR 1394; L 2005 c 97 art 3 s 19

Statutory Authority: MS s 116C.695; 216F.05