(a) General Requirements. Blasting shall be
conducted to prevent injury to persons, damage to public or private property
outside the permit area, adverse impacts on any underground mine, and change in
the course, channel or availability of surface water or ground water outside
the permit area.
(b) Airblast
(1) Limits
(A) Airblast shall not exceed the maximum
limits listed below at the location of any dwelling, public building, school,
church, community or institutional building outside the permit area, except as
provided in § 5355(e).
|
Lower Frequency Limit Of Measuring System, In
Hz (+/- 3 dB)
|
Maximum Level (in dB)
|
| 0.1 Hz or lower--flat
response1
|
134 peak. |
| 2 Hz or lower--flat response |
133 peak. |
| 6 Hz or lower--flat response |
129 peak. |
| C-weighted--slow response
n1
|
105 peak dBC |
1Only when approved by the
Permit Board.
(B) If
necessary to prevent damage, the Permit Board shall specify lower maximum
allowable airblast levels than those of § 5355(b)(1)(A) for use in the vicinity
of a specific blasting operation.
(2) Monitoring
(A) The operator shall conduct periodic
monitoring to ensure compliance with the airblast standards. The Permit Board
may require airblast measurement of any or all blasts and may specify the
locations at which such measurements are taken.
(B) The measuring systems shall have an
upper-end flat-frequency response of at least 200 Hz.
(c) Flyrock. Flyrock traveling in
the air or along the ground shall not be cast from the blasting site:
(1) more than one-half the distance to the
nearest dwelling or other occupied structure;
(2) beyond the area of control required under
§ 5353(c); or
(3) beyond the permit
boundary.
(d) Ground
Vibration
(1) General. In all blasting
operations, except as otherwise authorized in §5355(e), the maximum ground
vibration shall not exceed the values approved in the blasting plan required
under § 2707. The maximum ground vibration for protected structures listed in §
5355(d)(2)(A) shall be established in accordance with either the maximum
peak-particle-velocity limits of § 5355(d)(2), the scaled-distance equation of
§ 5355(d)(3), the blasting-level chart of §5355(d)(4), or by the Permit Board
under § 5355(d)(5). All structures in the vicinity of the blasting area not
listed in § 5355(d)(2)(A), such as water towers, pipelines and other utilities,
tunnels, dams, impoundments and underground mines, shall be protected from
damage by establishment of a maximum allowable limit on the ground vibration,
submitted by the operator in the blasting plan and approved by the Permit
Board.
(2) Maximum Peak Particle
Velocity
(A) The maximum ground vibration
shall not exceed the following limits at the location of any dwelling, public
building, school, church, community or institutional building outside the
permit area:
| Distance (D) From the Blasting Site, in Feet |
Maximum Allowable Peak Particle Velocity (V max) for
Ground Vibration, in in/sec1
|
Scaled-Distance Factor to be Applied without Seismic
Monitoring2
|
| to 300 |
1.25 |
50 |
| 301 to 5,000 |
1.00 |
55 |
| 5,001 and beyond |
0.75 |
6 |
1 Ground vibration shall be
measured as the particle velocity. Particle velocity shall be recorded in three
mutually perpendicular directions. The maximum allowable peak particle velocity
shall apply to each of the three measurements.
2 Applicable to the
scaled-distance equation of §5355(d)(3)
(A).
(B) A seismographic record shall be provided
for each blast.
(3)
Scaled-Distance Equation
(A) An operator may
use the scaled-distance equation, W = (D/Ds)2, to
determine the allowable charge weight of explosives to be detonated in any
8-millisecond period, without seismic monitoring; where W = the maximum weight
of explosives, in pounds; D = the distance, in feet, from the blasting site to
the nearest protected structure; and Ds = the scaled-distance factor, which may
initially be approved by the Permit Board using the values for scaled-distance
factor listed in § 5355(d)(2)(A).
(B) The development of a modified
scaled-distance factor may be authorized by the Permit Board on receipt of a
written request by the operator, supported by seismographic records of blasting
at the minesite. The modified scaled-distance factor shall be determined such
that the particle velocity of the predicted ground vibration will not exceed
the prescribed maximum allowable peak particle velocity of § 5355(d)(2)(A), at
a 95-percent confidence level.
(4) Blasting-Level Chart.
(A) An operator may use the ground-vibration
limits in Figure 1 to determine the maximum allowable ground vibration.
Figure 1. Alternative blasting level criteria. (Source:
Modified from figure B-1, Bureau of Mines R18507)
Click
Here To View Image
(B) If the Figure 1 limits are used, a
seismographic record including both particle velocity and vibration-frequency
levels shall be provided for each blast. The method for the analysis of the
predominant frequency contained in the blasting records shall be approved by
the Permit Board before application of this alternative blasting
criterion.
(5) The
maximum allowable ground vibration shall be reduced by the Permit Board beyond
the limits otherwise provided by this Section, if determined necessary to
provide damage protection.
(6) The
Permit Board may require an operator to conduct seismic monitoring of any or
all blasts or may specify the location at which the measurements are taken and
the degree of detail necessary in the measurement.
(e) The maximum airblast and ground-vibration
standards of § 5355(b) and (d) shall not apply at the following locations:
(1) at structures owned by the permittee and
not leased to another person; or
(2) at structures owned by the permittee and
leased to another person, if a written waiver by the lessee is submitted to the
Department before blasting.