12 Miss. Code. R. 3-2.1-1-01025-1.01 - DESCRIPTION
A. Scope: Submit a Schedule of
Values to the Professional at least ten (10) days prior to submitting
the first Application for Payment. Upon the Professional's request, the
Contractor will provide supportive data substantiating their correctness. Use
Schedule of Values only as basis for Contractor's Application
for Payment.
B. Form of Submittal:
Submit Schedule of Values on AIA Document G703, or computer generated form
containing similar style, using Table of Contents of these Specifications as
basis for format for listing costs of work for sections under Divisions 2-16.
Identify each line item with number and title as listed in Table of Contents in
these Specifications.
C. Preparing
Schedule of Values:
1. Itemize separate line
item cost for each of the following general cost items: Performance and Payment
Bonds, field supervision and layout, temporary facilities and
controls.
2. Itemize separate line
item cost for work required by each Section of these Specifications. Break down
installed cost with overhead and profit.
3. For each line item which has installed
value of more than $20,000, break down costs to list major products for
operations under each item, rounding figures to nearest dollar. Make sum of
total costs of all items listed in Schedule equal to total Contract
sum.
D. Preparing
Schedule of Unit Material Values:
1. Submit
separate Schedule of unit prices for materials to be stored on which progress
payments will be made. Make form of submittal parallel to Schedule of Values
with each line item identified same as line item in Schedule of Values. Include
in unit prices only: cost of material, delivery, unloading at site, and sales
tax.
2. Make sure unit prices
multiplied by quantities equal material cost of that item in Schedule of
Values.
E. Review and
Resubmittal: After Professional's review, if requested, revise and resubmit
Schedule of Values in same manner.