12 Miss. Code. R. 3-2.1-1-01310-1.01 - DESCRIPTION
A. Scope: Provide projected construction
schedules for entire work and revise periodically. The following is a minimum
requirement and other type schedules are acceptable with Owner's approval. This
type of schedule is acceptable for any Project whose initial Contract award
amount if less than one (1) million dollars ($1,000,000).
B. Form of Schedules: Prepare in form of
horizontal bar chart.
1. Provide separate
horizontal bar column for each trade or operation.
2. Place in order of the Table of Contents of
Specifications.
3. Identify each
column by major Specification section number.
4. Identify the first work day of each week
by horizontal time scale.
5. Scale
and space to allow for updating.
C. Contents of Schedule:
1. Provide complete sequence of construction
by activity.
2. Indicate dates for
beginning and completion of each stage of construction.
3. Identify work of separate floors, separate
phases, or other logically grouped activities.
4. Show projected percentage of completion
for each item of work as of first day of month.
D. Updating:
1. Show all changes occurring since previous
submission of updated schedule.
2.
Indicate progress of each activity and completion dates.
E. Submittals:
1. Submit initial schedules to the
Professional within fifteen (15) days after date of Notice to
Proceed.
2. Submit to Professional
periodically updated schedules accurately depicting progress to first day of
each month.
3. Submit two (2)
copies, one (1) to be retained by the Professional and the other forwarded to
the Owner.