12 Miss. Code. R. 3-2.1-1-01311-1.05 - SCHEDULES
A. Critical Path Methods: Prepare network
analysis diagrams and supporting mathematical analyses using the
Critical Path Method under Concepts and
Methods as outlined in the AGC's The Use of CPM in Construction, A
Manual for General Contractors and the Construction Industry.
B. Order of Work: Illustrate order and
interdependence of activities and sequence of Work; how start of a given
activity depends on completion of preceding activities, and how completion of
the activity may restrain start of subsequent activities.
C. Complete Sequence of Construction:
Illustrate complete sequence of construction by activity, identifying work of
separate stages. Provide dates for submittals and return of submittals; dates
for procurement and delivery of products; and dates for installation and
provision for testing. Provide legend for symbols and abbreviations
used.
D. Mathematical Analysis:
Tabulate each activity of detailed network diagrams, using calendar dates, and
identify for each activity:
1. Preceding and
following event numbers
2. Activity
description
3. Estimated duration
of activity, in maximum thirty (30) day intervals
4. Earliest start date
5. Earliest finish date
6. Actual start date
7. Actual finish date
8. Latest start date
9. Latest finish date
10. Total and free float
11. Monetary value of activity (keyed to
Schedule of Values)
12. Percentage of activity
completed
13.
Responsibility
E.
Analysis Program: Capable of compiling monetary value of completed and
partially completed activities, of accepting revised completion dates, and
recomputation of all dates and floats.
F. Required Sorts: List activities in sorts
or groups:
1. By preceding work item or event
number from lowest to highest
2. By
amount of float, then in order of early start
3. By responsibility in order of earliest
possible start date
4. In order of
latest allowable start dates
5. In
order of latest allowable finish dates
6. Contractor's periodic payment request
sorted by Schedule of Values listings, Specifications
section
7. Listing of basic input
data which generates the report
8.
Listing of activities on the critical path
9. Monthly cash flow
G.
Schedule of Values:
Coordinate contents with Schedule of Values in Section
01300.