12 Miss. Code. R. 3-2.1-1-01311-1.08 - UPDATING SCHEDULES
A. Schedules:
Maintain schedules to record actual start and finish dates of completed
activities.
B. Progress: Indicate
progress of each activity to date of revision, with projected completion date
of each activity. Update diagrams to graphically depict current status of
Work.
C. Modifications: Identify
activities modified since previous submittal, major changes in Work, and other
identifiable changes.
D. Changes:
Indicate changes required to maintain Date of Substantial or Total Completion.
These changes will be made only with the approval of the
Professional.
E. Extensions:
Contract completion time will be adjusted only for causes specified in the
Contract. Requests for an extension of the contract completion date by the
Contractor shall be supported with a justification, CPM data and supporting
evidence as the Owner may deem necessary for determination as to whether or not
the Contractor is entitled to an extension of time under the provisions of the
Contract. Submission of proof based on revised activity logic duration and
costs is obligatory to any approvals. The schedule must clearly display that
the Contractor has used, in full, all the float time available for the work
involved in the request. The Owner's determination as to the total number of
days of contract extension shall be based upon the current computer-produced
calendar-dated schedule for the time period in question and all other relevant
information. Actual delays in activities which, according to the
computer-produced calendar-dated schedule, do not affect the extended and
predicted contract completion dates shown by the critical path in the network,
will not be the basis for a change to the contract completion date. The Owner
will, within a reasonable time after receipt of such justification and
supporting evidence, review the facts and advise the Contractor in writing of
the Owner's decision. The Contractor shall submit each request for a change in
the contract completion date to the Owner. The Contractor shall include as a
part of each change order proposal, a sketch showing all CPM revisions,
duration changes, and cost changes, for the work in question and its
relationship to other activities on the approved arrow diagram.
F. Substantiate: Submit sorts required to
support recommended changes.
G.
Report: Provide narrative report to define problem areas, anticipated delays,
and impact on the schedule. Report corrective action taken or proposed and its
effect.