12 Miss. Code. R. 3-2.1-1-01630-1.04 - SUBSTITUTIONS
A. Professional will not consider requests
for substitutions during bidding.
B. Within thirty (30) days after the Contract
has been signed, the Professional will consider formal requests from the
Contractor for substitution of products in place of those specified. Submit
five (5) copies of the request for substitutions. Include in the request:
1. Complete data substantiating compliance of
proposed substitutions with Contract Documents.
2. For products:
a. Product identification including
Manufacturer's name and address.
b.
Manufacturer's literature: Product description, performance and test data and
reference standards.
c.
Samples.
d. Name and address of
similar products on which product was used and date of installation.
3. For construction methods:
a. Detailed description of proposed
method.
b. Drawings illustrating
methods.
4. Itemized
comparison of proposed substitutions with product or method
specified.
5. Data relating to
changes in construction schedule.
6. Accurate cost data on proposed
substitution in comparison with product or method specified.
C. In making request for
substitution, Contractor represents:
1.
Proposed product, or method, has been investigated and determined that it is
equal or superior in all respects to that specified.
2. The same guarantee will be provided for
substitutions as for product or method specified.
3. Installation of accepted substitutions
will be coordinated into the Work, making such changes required of work to be
compete in all respects.
4. All
claims for additional costs related to substitution which consequently become
apparent will be waived.
5. Cost
data is complete and includes all related costs under the Contract.
D. Substitutions will not be
considered if:
1. Indicated, or implied, on
shop drawings or product data submittals without formal request submitted in
accordance with this Section.
2.
Acceptance will require substantial revision of Contract Documents.
3. In the Professional's judgment, the
product, or material, is not equal.