12 Miss. Code. R. 3-2.1-1-01700-1.02 - FINAL INSPECTIONS
A. Professional's
Inspection: The Contractor shall make written request for a final inspection to
the Professional; notice to be given ten (10) days prior to the inspection. A
list of any deficiencies, compiled by the Professional, will be corrected by
the Contractor. If, in the Professional's judgement, the Project is not ready
for a final inspection, the Professional may schedule another
inspection
B. Owner's Inspection:
After the Professional has ascertained the Project to be ready, an Owner's
inspection will be scheduled within ten (10) days thereafter. The Contractor
will have ten (10) days after the Owner's acceptance to make any corrections of
punch list items and to submit closeout documents.
C. Correction of Work Before Final Payment:
The Contractor shall promptly remove from the Owner's premises all materials
condemned for failure to conform to the Contract, whether incorporated in the
Work or not, and the Contractor shall, at his own expense, replace such
condemned materials with those conforming to the requirements of the Contract.
Failure to remedy such defects after ten (10) days written notice will allow
the Owner to make good such defects and such costs shall be deducted from the
balance due the Contractor, or charged to the Contractor in the event no
payment is due.