12 Miss. Code. R. 3-2.1-600.40 - ADDENDA
Should Addendum be necessary, the Professional will issue them as expeditiously as possibly to all parties concerned prior to the time for receiving bids. However, no addendum should be issued within two (2) working days of the receipt of bids unless such addendum also amends the bid opening to a date not less than five (5) working days after the date of the addendum. Bidders should acknowledge any Addendum on the Proposal Form. All Addenda will be incorporated into the Construction Documents and become a part of the Construction Contract.