12 Miss. Code. R. 3-2.1-700.4 - SCHEDULE OF VALUES

A Schedule of Values, typewritten on AIA Document G702A, will be submitted by the Contractor to the Professional at least ten (10) days prior to submitting the first Application for Payment. Upon the Professional's request, the Contractor may be asked to support the values stated on the Schedule with data substantiating their correctness.

Notes

12 Miss. Code. R. 3-2.1-700.4
Amended 8/14/2016

State regulations are updated quarterly; we currently have two versions available. Below is a comparison between our most recent version and the prior quarterly release. More comparison features will be added as we have more versions to compare.


No prior version found.